A.
The municipality shall inspect all phases of the installation of the best management practices (BMPs) and/or stormwater management (SWM) facilities as deemed appropriate by the municipality.
B.
During any stage of the work, if the municipality determines that the BMPs and/or stormwater management facilities are not being installed in accordance with the approved SWM site plan, the municipality shall revoke any existing permits or other approvals and issue a cease-and-desist order until a revised SWM site plan is submitted and approved, as specified in this chapter and until the deficiencies are corrected.
C.
An inspection of all BMPs and/or stormwater management facilities may be conducted by the municipality to confirm compliance with the approved SWM site plan prior to the issuance of any occupancy permit.