A. 
The municipality shall inspect all phases of the installation of the best management practices (BMPs) and/or stormwater management (SWM) facilities as deemed appropriate by the municipality.
B. 
During any stage of the work, if the municipality determines that the BMPs and/or stormwater management facilities are not being installed in accordance with the approved SWM site plan, the municipality shall revoke any existing permits or other approvals and issue a cease-and-desist order until a revised SWM site plan is submitted and approved, as specified in this chapter and until the deficiencies are corrected.
C. 
An inspection of all BMPs and/or stormwater management facilities may be conducted by the municipality to confirm compliance with the approved SWM site plan prior to the issuance of any occupancy permit.
A. 
The applicant and/or developer shall be responsible for providing as-built plans of all SWM BMPs included in the approved SWM site plan. The as-built plans and an explanation of any discrepancies with the construction plans shall be submitted to the municipality.
B. 
The as-built submission shall include a certification of completion signed by a qualified professional verifying that all permanent SWM BMPs have been constructed according to the approved plans and specifications. If any licensed qualified professionals contributed to the construction plans, they must sign and seal the completion certificate.
C. 
The applicant and/or developer shall be responsible for providing the latitude and longitude coordinates for all permanent SWM BMPs, at the central location of each BMP.
D. 
After receipt of the completion certification by the municipality, the municipality may conduct a final inspection.