(a)
Compliance.
A person commits an offense if the person places or causes to be placed any facilities within the right-of-way in any other manner than specified in this division.
(b)
Permit required.
A person shall obtain an excavation permit prior to performing any excavation, construction, relocation, removal, installation, repair, or maintenance of facilities within the right-of-way. An excavation permit is required for new construction and replacement or upgrading of a utility provider’s network in the right-of-way, either aerial or underground.
(c)
Exceptions.
The following work undertaken by a person does not require an excavation permit:
(1)
Work that is incidental in nature;
(2)
Work required by emergency conditions, if the registration holder complies with subsection (d) hereof;
(3)
Work that obstructs the flow of vehicular traffic on a street, alley, or sidewalk for less than four hours, if the person has complied with the following requirements:
(A)
The registration holder has submitted a traffic-control plan to the city manager in a form approved by the city manager;
(B)
The city manager has approved the traffic-control plan;
(C)
The work is performed in compliance with the traffic-control plan; and
(D)
Unless the work is performed under emergency conditions, the person has given the city manager four hours’ written notice of the proposed work;
(4)
Work performed to initiate service to an individual customer’s property, as long as the requirements of subsection (3) are met, if applicable; or
(5)
Work performed by a contractor on behalf of the city.
(d)
Emergency work.
When performing work required by emergency conditions, the registration holder shall notify the city manager as promptly as possible. An after-hours number for the city manager will be provided to the registration holder in case emergency conditions occur after normal business hours. The city manager shall determine if any city employee shall be required to be present for on-site inspection during emergency repairs. A registration holder who performs the emergency work shall submit to the city, as soon as practicable, a reasonably detailed description of the work performed in the right-of-way and an updated map of the facilities that were relocated, if any.
(Ordinance 422-2007, sec. 10, adopted 4/17/07)