For the purposes of this chapter:
HOT PATCH
The installation of a mixture of asphalt to restore property
within the right-of-way to its previous condition subsequent to the
construction or excavation of a site required for the placement, replacement
or removal of a pole of a utility pole or an underground facility
pursuant to this chapter.
POLE
In addition to its commonly accepted meaning, any wires or
cable connected thereto, and any replacements which are similar in
construction and use.
UNDERGROUND FACILITY
One or more underground pipes, cables, wires, lines or other
structures used for the supplying and distribution of electricity
for light, heat or power, or for the furnishing of telephone or other
telecommunications service.
Any penalties imposed in accordance with §
395-4 hereof shall be collected or enforced in a summary manner, without jury, in any court of competent jurisdiction, including, but not limited to, the Municipal Court of the Township of Verona, in accordance with the procedures provided by the Penalty Enforcement Law (N.J.S.A. 2A:58-1 et seq.).