(a)
Drill site conditional use permit.
No person shall establish a drill site nor engage in oil and gas drilling or production activities without first obtaining a conditional use permit in accordance with this article and the requirements set forth in this Code of Ordinances, article 14.02, division 11: Conditional Use Permit District (CU). A separate conditional use permit shall be required for each drill site. Once issued, the conditional use permit shall continue to apply to the site after any part of it has been reduced and converted to an operation site.
(b)
Well permit.
(1)
No person shall engage in oil and gas production activities without first obtaining a well permit. Applications for a well permit shall not be considered by the town without:
(2)
Well permit applications shall not be reviewed by the town staff prior to the submission of the required fees associated with these activities. A separate well permit and well permit fee is required for each well.
(c)
Pipeline permit.
No person shall engage in oil and gas pipeline activities without first obtaining a pipeline permit. Applications for a pipeline permit shall not be considered by the town without an approved site plan. Pipeline permits shall not be reviewed by the town staff prior to the submission of the required fees associated with pipeline activities. Permit application requirements for pipelines are set forth in division 3 of this article.
(d)
Seismic survey permit.
No person shall engage in seismic surveying activities without first obtaining a seismic survey permit. A separate seismic survey permit application and fee shall be submitted to the town for each seismic survey that the person wishes to execute. The permit application requirements are set forth in section 14.04.041 of this article.
(Ordinance 2011-12-6D, sec. 2.03, adopted 12/6/11)