(a)
For any of the activities regulated by this chapter, unless preparation of a stormwater management (SWM) site plan is specifically exempted, the preliminary or final approval of subdivision and/or land development plans, the issuance of any building or occupancy permit, the commencement of any earth disturbance activity shall not proceed until the property owner or applicant or his/her agent has received written approval from the Township of a SWM site plan that demonstrates compliance with the requirements of this chapter, and a written approval of an adequate erosion and sediment (E&S) control plan from the Township or Montgomery County Conservation District, when and as required.
(b)
SWM site plans approved by the Township, in accordance with Article III, shall be on site throughout the duration of the regulated activity.
(c)
The Township may, after consultation with the Department of Environmental Protection (DEP), approve measures for meeting the state water quality requirements other than those in this chapter, provided that they meet the minimum requirements of, and do not conflict with, state law including but not limited to the Clean Streams Law.
(d)
For all regulated earth disturbance activities, erosion and sediment (E&S) control best management practices (BMPs) shall be designed, implemented, operated and maintained during the regulated earth disturbance activities (e.g., during construction) to meet the purposes and requirements of this chapter and to meet all requirements under Title 25 of the Pennsylvania Code and the Clean Streams Law. Various BMPs and their design standards are listed in the Erosion and Sediment Pollution Control Manual, No. 363-2134-008 (April 15, 2000), as amended and updated.
(e)
Impervious areas:
(1)
The measurement of impervious areas shall include all of the impervious areas in the total proposed development even if development is to take place in stages.
(2)
For development taking place in stages, the entire development plan must be used in determining conformance with this chapter.
(3)
For projects that add impervious area to a parcel, the total impervious area within the limits of disturbance is subject to the requirements of this chapter area.
(f)
Stormwater flows onto adjacent property shall not be created, increased, decreased, relocated, or otherwise altered without written notification of the adjacent property owner(s) by the applicant. Such stormwater flows shall be subject to the requirements of this chapter.
(g)
All regulated activities shall include such measures as necessary to:
(1)
Protect health, safety and property;
(2)
Meet the water quality goals of this chapter by implementing measures to:
A.
Minimize disturbance to floodplains, wetlands, and wooded areas.
B.
Create, maintain, repair or extend riparian buffers.
C.
Avoid erosive flow conditions in natural flow pathways.
D.
Minimize thermal impacts to waters of the Commonwealth.
E.
Disconnect impervious surfaces (i.e., disconnected impervious areas, DIAs) by directing runoff to pervious areas, wherever possible.
(3)
To the maximum extent practicable, incorporate the techniques for low-impact development practices (e.g., protecting existing trees, reducing areas of impervious surface, cluster development, and protecting open space) described in the Pennsylvania Stormwater Best Management Practices Manual, Pennsylvania Department of Environmental Protection (PADEP) No. 363-0300-002(2006).
(h)
The design of all facilities over karst features shall include an evaluation of measures to minimize adverse effects.
(i)
Infiltration BMPs should be dispersed on site, made as shallow as practicable, and located to maximize use of natural on-site infiltration features while still meeting the other requirements of this chapter.
(j)
Normally dry, open top storage facilities should completely drain both the volume control and rate control capacities over a period of time not less than 24 and not more than 72 hours from the end of the design storm.
(k)
Design storm volumes and precipitation intensities to be used in the analysis of discharge or runoff should be obtained from the Precipitation-Frequency Atlas of the United States, Atlas 14, Volume 2, Version 3.0, U.S. Department of Commerce, National Oceanic and Atmospheric Administration (NOAA), National Weather Service, Hydrometeorological Design Studies Center, Silver Springs, Maryland. NOAA's Atlas 14 can be accessed at: http://hdsc.nws.noaa.gov/hdsc/pfds/.
(l)
For all regulated activities, SWM BMPs shall be designed, implemented, operated, and maintained to meet the purposes and requirements of this chapter and to meet all requirements under Title 25 of the Pennsylvania Code, the Clean Streams Law, and the Storm Water Management Act.
(m)
Various BMPs and their design standards are listed in the Pennsylvania Stormwater Best Management Practices Manual (PA BMP Manual).
(n)
Storm sewers (pipes or other structures) shall be reinforced concrete pipe or high-density polyethylene (when approved by the Township Engineer), have a minimum grade of 0.5% and a minimum inside diameter of 18 inches or a cross-sectional area of 254 square inches. Roof drains or yard drains shall not connect to any sanitary sewer and shall not discharge water directly over any sidewalk. Storm drainage facilities should be located within the paved areas of roadways. Where storm sewers discharge into existing drainage channels at an angle greater than 30° with the downstream channel flow, the far side bank shall be stabilized by the use of riprap or other approved stabilization method. The stabilization shall be designed to prevent erosion and frost heave under and behind the stabilizing media.
(o)
Maintenance of all drainage facilities and watercourses, both existing and proposed, within the proposed site shall be the responsibility of the developer until such time as one of the following is accomplished:
(1)
A right-of-way for these facilities is offered for dedication by the developer and is accepted by the Township, at which time it shall then be the responsibility of the Township.
(2)
An easement acceptable to the Township is established. In the case of a subdivision, the maintenance shall then be the responsibility of the individual lot owners over whose property the easement passes. For land developments or regulated earth disturbance activities, the maintenance shall thereafter be the responsibility of the owner.
(3)
A homeowners' association, approved by the Township, assumes responsibility for the maintenance of the development, including the maintenance of the watercourses and/or drainage facilities, provided that the Township Engineer approves the assumption of maintenance of such facilities.
(p)
All proposed roadways shall be constructed with an underdrain system consisting of six-inch perforated pipe wrapped in a Class 1 geotextile material. The underdrain shall be bedded with a minimum of six inches of 2B stone. The bedding material shall extend to the bottom of the base course. The underdrain shall discharge to an inlet.
(q)
All pipe and inlets shall meet material capacity and construction specifications as outlined in the latest revisions of the PENNDOT Form 408 and the PENNDOT Design Manual or as outlined in the Township specification as approved by resolution of the Board of Supervisors. Inlets at street intersections shall be placed on the tangent and not on the curved portion.
(r)
Design flow rate. The storm drain system shall be designed to carry a 100-year peak flow rate. The design 100-year peak flow rate into each inlet shall be indicated on the stormwater drainage plan. The 100-year flow rate shall be determined by the rational formula. [Rational Formula is defined in § 1241.411(b).]
(s)
Inlet capacity. All inlets must be designed to accommodate the 100-year peak flow rate. The capacity of all C-type, M-type or S-type inlets shall be determined from the Commonwealth of Pennsylvania Department of Transportation Design Manual, Part 2, Highway Design.
(t)
Allowable headwater depth. At all inlets or manholes, the maximum allowable headwater depth shall be one foot below the top of the inlet grate or the manhole cover.
(u)
Manholes. Manholes shall not be more than 400 feet apart where pipe sizes of 24 inches or less are used, and not more than 450 feet apart where larger sizes are installed. Manholes shall be installed at all points of abrupt change in alignment.
(v)
Maximum depth of detention basins. The maximum depth of water in a detention basin shall not exceed four feet.
(w)
Emergency spillway. Whenever possible, the emergency spillway for detention basins shall be constructed on undisturbed ground. Emergency spillways shall be constructed of reinforced concrete, vegetated earth or other approved material. All emergency spillways shall be constructed so that the detention basin berm is protected against erosion. The minimum capacity of all emergency spillways shall be equal to the peak flow rate from the post-development 100-year design storm. Emergency spillways shall extend along the upstream and downstream berm embankment slopes. The upstream edge of the emergency spillway shall be a minimum of three feet below the spillway crest elevation. The downstream slope of the spillway shall, as a minimum, extend to the top of the berm embankment. The emergency spillway shall not discharge over earthen fill and/or easily erodible material. The discharge path of the emergency spillway shall be evaluated to ensure that downstream properties or structures are not impacted.
(x)
Antiseep collars. Antiseep collars shall be poured-in-place concrete and installed around the principal pipe barrel within the normal saturation zone of the detention basin berms. The collar shall be poured against the pipe bell. The antiseep collars and their connections to the pipe barrel shall be watertight. The antiseep collars shall extend a minimum of two feet beyond the outside of the principal pipe barrel. The spacing between collars shall be 16 feet. The use of an O-ring pipe shall be required for all basin discharge pipes.
(y)
Freeboard. "Freeboard" is the difference between the design flow elevation in the emergency spillway and the top of the settled detention basin embankment. The minimum freeboard shall be one foot and the maximum freeboard shall be two feet.
(z)
Slope of detention basin embankment. The maximum slope of earthen detention basin embankments shall be three to one. The top or toe of any slope shall be located a minimum of 10 feet from any property line. Whenever possible, the side slopes and basin shape shall be amenable to the natural topography. Straight side slopes and rectangular basins shall be avoided whenever possible.
(aa)
Width of berm. The minimum top width of detention basin berms shall be 10 feet.
(ab)
Energy dissipaters. Energy dissipating devices (riprap, level spreaders, end sills, etc.) shall be placed at all basin outlets. Forebays or split flow controls are encouraged at the inlet to all basins. When a forebay or split flow control is not used, an energy dissipating device shall be used. Riprap at the inlet to a basin shall extend to the bottom of the basin.
(ac)
Key trench. All basin berms in fill areas are to have a key trench. The minimum depth shall be one foot and increased to a depth of three feet at the maximum point of fill. The minimum width of the key trench shall be eight feet.
(ad)
Design flow standard. All culverts and drainage channels shall be designed to carry a flow rate equal to a 100-year, twenty-four-hour storm (Soil Cover Complex Method by the NRCS, Technical Release No. 55).