Any owner or Developer of any lot, tract, or parcel of land located within the corporate limits of the City or within its jurisdiction who wishes to subdivide such land shall conform to the process shown in Figure 53 or Figure 54.
Figure 53. Summary of the Subdivision Process (Hold Final Plat) | | Figure 54. Summary of the Subdivision Process (Security) |
Pre-Application Meeting | | Pre-Application Meeting |
Optional meeting to discuss proposal with City staff | | Optional meeting to discuss proposal with City staff |
 | |  |
Sketch Plan | | Sketch Plan |
Generalized layout of a larger site or phased development, if applicable | | Generalized layout of a larger site or phased development, if applicable |
 | |  |
Preliminary Plat | | Preliminary Plat |
Detailed layout of the site to be developed | | Detailed layout of the site to be developed |
 | |  |
Construction Plans | | Construction Plans, Final Plat Application, and Security |
Construction details for the proposed improvements | | Construction detail, application for Final Plat, and required security |
 | |  |
Construction of the Improvements | | Final Plat |
Construction of the improvements | | Final Plat approved and filed |
 | |  |
Inspection and Acceptance | | Construction of Improvements |
Inspection of the improvements and letter of acceptance | | Construction of the improvements |
 | |  |
Final Plat | | Inspection and Acceptance |
Filed with the County once improvements have been accepted by the City | | Inspection of the improvements and letter of acceptance |
 | |  |
Zoning Procedures | | Zoning Procedures |
Site Plan, Building Permit, Construction, Certificate of Occupancy | | Site Plan, Building Permit, Construction, Certificate of Occupancy |
(Ordinance 2017-13 adopted 10/2/2017)