A.
Purpose. The purpose of this section is to ensure that Public Improvements are installed to serve a development in accordance with all Subdivision Regulations and Development Standards.
B.
Submitting Plans. Plans shall be submitted in accordance with Development Services Director's requirements, as provided in the Development Application Forms. Incomplete Construction Plans shall not be accepted and such plans shall be returned to the Applicant.
C.
Responsible Official and Decision Authority for Construction Plans.
1.
Review and Approval Action. The City Engineer shall be the Responsible Official for review and approval of Construction Plans.
2.
Outside Review. If an outside consultant is contracted to review Construction Plans, then the Applicant shall reimburse the City for the review fees.
3.
Decision-Maker Options. In this capacity, therefore, the City Engineer shall approve, approve subject to modifications, or deny the Construction Plans.
D.
Approval Required and Timing of Construction. Construction Plans must be approved in accordance with this Subsection 3.04, Construction Plans and Procedures prior to the approval or recordation of the Final Plat, unless otherwise stated within this UDC.
E.
Criteria for Approval. The City Engineer shall approve Construction Plans if:
1.
The Construction Plans are consistent with the approved Preliminary Plat, or the proposed Final Plat; and
2.
The Construction Plans conform to the subject property's zoning and Planned Development (PD) standards (including zoning design standards), and to the standards for adequate public facilities, contained in these Subdivision Regulations and Development Standards and all other applicable City codes.
G.
Expiration Date for Construction Plans. The approval of Construction Plans shall remain in effect for a period of one (1) year from the date of approval, or for the duration of construction of the project, provided that Progress towards Completion of the project continues to be demonstrated, unless the Construction Plans are extended in accordance with subsection H below.
H.
Extension of Construction Plans beyond Expiration Date.
2.
Decision by the City Engineer.
a.
The City Engineer will review the extension request, and shall approve, approve with conditions, or deny the extension request within thirty (30) calendar days following the date of the extension request.
b.
Should the City Engineer fail to act on an extension request within thirty (30) calendar days, the extension shall be deemed to be approved.
3.
Consideration. The City Engineer shall extend Construction Plans approval for a period of six (6) additional months beyond the expiration date if:
a.
A Final Plat has been submitted, approved or filed of record for any portion of the property shown on the Construction Plans;
b.
The Construction Plans comply with new ordinances (i.e., ordinances that have been adopted after approval of the original Construction Plans) that impact the health, safety and general welfare of the City;
c.
Demonstrable forward progress has been made to proceed with construction or required improvements; and
4.
Conditions. In granting an extension, the City Engineer may impose such conditions as are needed to ensure that the land will be developed in a timely fashion and that the public interest is served. Any extension may be predicated upon compliance with new development regulations or the Applicant waiving any vested rights.
5.
Total Extension. A second six (6) month extension may be requested using the same process outlined above.
(Ordinance 2017-13 adopted 10/2/2017; Ordinance 2025-47 adopted 10/8/2025)