[Ord. No. 511, 2/14/2005;
as amended by Ord. No. 612, 9/12/2022]
1. The Municipal Engineer or his municipal designee shall inspect all
phases of the installation of the permanent BMPs and/or stormwater
management facilities as deemed appropriate by the Municipal Engineer.
2. During any stage of the work, if the Municipal Engineer or his municipal
designee determines that the permanent BMPs and/or stormwater management
facilities are not being installed in accordance with the approved
stormwater management plan, the Municipality may revoke any existing
permits or other approvals and issue a cease and desist order until
a revised SWM site plan is submitted and approved, as specified in
this chapter, and until the deficiencies are corrected.
3. A final inspection of all BMPs and/or stormwater management facilities
shall be conducted by the Municipal Engineer or his municipal designee
to confirm compliance with the approved SWM site plan prior to the
issuance of any occupancy permit.
[Ord. No. 511, 2/14/2005;
as amended by Ord. No. 612, 9/12/2022]
1. The developer shall be responsible for providing as-built plans of
all SWM BMPs included in the approved SWM site plan for activities
involving regulated impervious surfaces. The as-built plans and all
explanation of any discrepancies with the construction plans shall
be submitted to the Municipality within three months of the completion
of construction of the SWM BMPs.
2. As-built plans shall show the location (including latitude and longitude
coordinates) and as-built conditions of all SWM BMPs and include the
following information: impervious surfaces included in the approved
SWM site plan; topographic contours; and existing, proposed, and built
impervious surfaces shown in the as-built drawings.
3. The as-built submission shall include a certification of completion
signed by a design professional verifying that all permanent SWM BMPs
have been constructed according to the approved plans and specifications.
4. The municipality will review the as-built submission for consistency
with the approved SWM site plan as well as actual conditions at the
project site. After receipt of the completion certification by the
Municipality, the Municipality may conduct a final inspection.
5. If an NPDES permit for stormwater discharges associated with construction
activities was required for the regulated activity, a notice of termination
(NOT) approval must be obtained upon completion of construction prior
to final approval of the project by the Municipality.