A.
Pre-application technical review meeting. At any point prior to the submittal of a preliminary subdivision plan an applicant may submit preliminary plans for review and comments by the Technical Review Team (TRT). The applicant shall contact the Planning Board Administrator to schedule a TRT meeting. During such TRT meeting, the applicant presents the preliminary plans to the TRT and is able to ask questions; from there members of the TRT ask questions and/or provide comments that should be considered when preparing subdivision plans.
B.
Pre-application preliminary subdivision plan application review. Prior to the finalization of a preliminary subdivision application package, an applicant may request a meeting with the Planning Board Administrator for the review of the application and/or subdivision plan. During such meeting the Planning Board Administrator can provide review of the application and/or subdivision plan for conformance with Article VI of these regulations, answer questions regarding the process, and/or conduct a site visit.
C.
Delivery of a preliminary subdivision application package.
(1)
Prior to the dropoff of a preliminary subdivision application package the applicant shall schedule a meeting with the Planning Board office for the delivery and review of the application. (Such meeting is anticipated to take approximately 30 minutes.)
(2)
During the scheduled preliminary application package dropoff to the Planning Board office, the Planning Board staff will review the preliminary subdivision application package, review the subdivision process with the applicant, prepare a timeline for review of the application, answer any questions that the applicant may have, and schedule the Technical Review Team (TRT) meeting and opening public hearing.
[Amended 4-4-2024]
(3)
Complete versus incomplete preliminary subdivision application package.
(a)
Complete preliminary subdivision application package. If a preliminary subdivision application package is complete and conforms to the requirements of Article VI of these regulations then the Planning Board office shall sign Form 4, Preliminary Subdivision Application Submittal, City Clerk Receipt, prepared by the applicant. The Planning Board office shall also provide the applicant with Form 6, Preliminary Subdivision Plan Checklist, that shall be also filed with the City Clerk.
(b)
Incomplete preliminary subdivision application package. If a preliminary subdivision application package is incomplete and/or does not conform to the requirements of Article VI and no waivers were requested for submittal relief then the Planning Board office shall not sign Form 4, Preliminary Subdivision Application Submittal, City Clerk Receipt, and shall provide the applicant with Form 6, Preliminary Subdivision Plan Checklist, which identifies the deficiencies that need to be resolved and resubmitted for review. At such time the applicant shall be given an opportunity to make the application complete. Incomplete applications shall not be deemed filed until such deficiencies have been resolved.
(4)
Once a preliminary subdivision application package is deemed complete by the Planning Board office then the applicant shall deliver Form 4, Preliminary Subdivision Application Submittal, City Clerk Receipt, one copy of an original Form 5, Preliminary Subdivision Plan Application, and Form 6, Preliminary Subdivision Plan Checklist, to the City Clerk's office, at which time the City Clerk will stamp the covers of the three documents and provide the applicant with copies of the covers bearing the City Clerk's stamps.
(5)
The applicant shall provide a copy of the stamped Form 4, Preliminary Subdivision Application Submittal, City Clerk Receipt, Form 5, Preliminary Subdivision Plan Application, and Form 6, Preliminary Subdivision Plan Checklist, to the Planning Board office.