(a)
No building or other structure shall be erected, moved, added to or structurally altered without a permit therefor, issued by the building official. No building permit shall be issued except in conformity with the provisions of this chapter, except after written order from the board of adjustment.
(b)
Application for building permit.
(1)
All applications for building permits shall be accompanied by plans, drawn to scale showing the actual dimensions and shape of the lot to be built upon; the exact sizes and locations on the lot of buildings already existing, if any; and the location and dimensions of the proposed building or alteration. The application shall include such other information as lawfully may be required by the building official, including existing or proposed building or alteration; existing or proposed uses of the building and land; the number of families, housekeeping units, or rental units the building is designed to accommodate; conditions existing on the lot; and such other matters as may be necessary to determine conformance with, and provide for the enforcement of this chapter.
(2)
One (1) copy, hardcopy or digital, of the plans shall be returned to the applicant by the building official, after he shall have marked such copy either as approved or disapproved and attested to same by his signature on such copy. The copy of the plans, similarly marked, shall be retained by the building official.
(c)
Building permit expiration.
(1)
If the work described in any building permit has not begun within ninety (90) days from the date of issuance thereof, said permit shall expire; it shall be cancelled by the building official; and written notice thereof shall be given to the persons affected.
(2)
If the work described in any building permit has not been substantially completed within two (2) years of the date of issuance thereof, said permit shall expire and be cancelled by the building official, and written notice thereof shall be given to the persons affected, together with notice that further work as described in the canceled permit shall not proceed unless and until a new building permit has been obtained.
(Ordinance 6555 adopted 12/5/2022)