1.
The Flood Plain Administrator shall review and evaluate the application and shall approve, approve with conditions, or deny the application within 60 days (or a time specified) of receipt of a correct and complete application.
2.
The Flood Plain Administrator shall determine whether the application contains the applicable elements required in these regulations and shall notify the applicant of the Flood Plain Administrator's determination.
3.
If the application is found insufficient and if the applicant corrects the identified deficiencies and resubmits the application, the Flood Plain Administrator shall notify the applicant whether the re-submitted application contains all the elements required by these regulations, as applicable.
4.
This process shall be repeated until the applicant submits a complete application containing all the elements required by these regulations, or the application is withdrawn.
5.
If after a reasonable effort the Flood Plain Administrator determines that the application remains incomplete, the Flood Plain Administrator shall deny the application and notify the applicant of missing elements. No further action shall be taken on the application by the Flood Plain Administrator until the application is re-submitted.
6.
A determination that an application contains the appropriate information for review does not ensure that the flood plain permit application will be approved or conditionally approved and does not limit the ability of the Flood Plain Administrator in requesting additional information during the review process.
(Ord. 895, 10-9-2012)