No person shall conduct any hauling of soil materials on public rights-of-way from or to the site of a grading operation, without first having obtained a haul route permit, if required, as specified in and subject to the requirements of the Engineering and Construction Manual.
Because this permit may be triggered by various factors (location, quantity of soil, truck trips, traffic, etc.), the city will determine if a haul route permit is required on a case-by-case basis prior to allowing any hauling operation to commence.
(Ord. 13-01 § 4)
To obtain a haul route permit, the applicant shall first file an application in writing on a form furnished by the city engineer for that purpose. The applicant shall submit a complete application with the required documentation and fee, the amount of which is set by city council resolution.
(Ord. 13-01 § 4)
Where soil materials are moved on public rights-of-way from or to the site of a grading operation, a haul route plan shall be approved by the city engineer in accordance with the Engineering and Construction Manual. Deviation from the designated haul route shall constitute a violation of the conditions of the permit issued under this title. Vehicular track-out shall be controlled, as directed by the city engineer, to prevent sediment deposition outside of the project site boundaries. All haul route requirements shall be in accordance with this title and the Engineering and Construction Manual.
(Ord. 13-01 § 4)