The following items shall be included in the SWM site plan:
A. 
Appropriate sections from the City's Subdivision and Land Development Ordinance,[1] and other applicable local ordinances, shall be followed in preparing the SWM site plans.
[1]
Editor's Note: See Ch. 475, Subdivision and Land Development.
B. 
The City shall not approve any SWM site plan that is deficient in meeting the requirements of this chapter. At its sole discretion and in accordance with this article, when a SWM site plan is found to be deficient, the City may either disapprove the submission or require a resubmission, or in the case of minor deficiencies, the City may accept submission of modifications.
C. 
Provisions for permanent access or maintenance easements for all physical SWM BMPs, such as ponds and infiltration structures, as necessary to implement the Operation and Maintenance (O&M) Plan discussed in Subsection E(9) below.
D. 
The following signature block for the City:
"(City Engineer or designee), on this date (date of signature), has reviewed and hereby certifies that the SWM site plan is in compliance with the Municipal Ordinance No. _____."
E. 
The SWM site plan shall provide the following information:
(1) 
The overall stormwater management concept for the project.
(2) 
A determination of site conditions in accordance with the BMP Manual.[2] A detailed site evaluation shall be completed for projects proposed in mined areas, carbonate geology, or karst topography, and other environmentally sensitive areas, such as brownfields; depending on site conditions, more stringent standards than those in this chapter may be imposed at the discretion of the City Engineer.
[2]
Editor's Note: See Reference 1 of § 424-901.
(3) 
Stormwater runoff design computations, and documentation as specified in this chapter, or as otherwise necessary to demonstrate that the maximum practicable measures have been taken to meet the requirements of this chapter, including the recommendations and general requirements in § 424-301; computations are required for all proposed stormwater management facilities.
(4) 
Expected project time schedule.
(5) 
A soil erosion and sediment control plan, where applicable, as prepared for and submitted to the approval authority, and in conformance with 25 Pa. Code Ch. 102.
(6) 
The effect of the project (in terms of runoff volumes, water quality, and peak flows) on surrounding properties and aquatic features and on any existing stormwater conveyance system that may be affected by the project.
(7) 
Plan and profile drawings of all SWM BMPs, including drainage structures, pipes, open channels, and swales.
(8) 
SWM site plan shall show the locations of existing and proposed on-lot wastewater facilities and water supply wells.
(9) 
The SWM site plan shall include an O&M plan for all existing and proposed physical stormwater management facilities. This plan shall address long-term ownership and responsibilities for O&M as well as schedules and costs for O&M activities.
(10) 
The SWM site plan shall include the following additional elements:
(a) 
Construction details of all proposed stormwater management facilities.
(b) 
A stormwater facility design narrative.
(c) 
A signature block containing the name, address, and phone number of the individual responsible for the operation and maintenance plan.
(d) 
A drainage area map with time of concentration paths shown.
(e) 
Existing contour intervals of two feet.
(f) 
All existing features on the property and within 50 feet of property.
(g) 
Floodplain and floodway limits.
(h) 
Proposed structures and proposed grades.
(i) 
Soil boundary lines and descriptions.
(j) 
Date of submission, north arrow, graphic scale, call before you dig note and reference number, location map, name of development, name and address of property owner, and individual preparing the SWM site plan.
(k) 
Existing and proposed easements.
(l) 
Statement signed by landowner stating that they cannot alter any stormwater management facility without prior permission of the City.
(11) 
A justification must be included in the SWM site plan if BMPs other than green infrastructure methods and LID practices are proposed to achieve the volume, rate and water quality controls under this chapter.
A. 
Five copies of the SWM site plan shall be submitted to the City of Hazleton Planning Commission for distribution as follows:
(1) 
Two copies to the City of Hazleton Planning Commission.
(2) 
One copy to the City Engineer.
(3) 
One copy to the County Conservation District.
(4) 
One copy to the County Planning Commission/Office.
B. 
Additional copies shall be submitted as requested by the City or DEP.
A. 
The SWM site plan shall be reviewed by the City Engineer for consistency with the provisions of this chapter. After review, the City Engineer shall provide a written recommendation for the City approval or disapproval of the SWM site plan. If it is recommended to disapprove the SWM site plan, the City Engineer shall state the reasons for the disapproval in writing. The City Engineer also may recommend approval of the SWM site plan with conditions and, if so, shall provide the acceptable conditions for approval in writing. The SWM site plan review and recommendations shall be completed within the time allowed by the Municipalities Planning Code for reviewing subdivision plans.
B. 
The City shall notify the applicant, in writing, within 45 days whether the SWM site plan is approved or disapproved. If the SWM site plan involves a subdivision and land development plan, the notification period is 90 days. If a longer notification period is provided by other statute, regulation, or ordinance, the applicant will be so notified by the City. If the City disapproves the SWM site plan, the City shall cite the reasons for disapproval in writing.
C. 
For any SWM site plan that proposed to use any BMPs other than green infrastructure and LID practices to achieve the volume and rate controls required under this chapter, the City will not approve the SWM site plan unless it determines that green infrastructure and LID practices are not practicable.
A modification to a submitted SWM site plan that involves a change in SWM BMPs or techniques, or that involves the relocation or redesign of SWM BMPs, or that is necessary because soil or other conditions are not as stated on the SWM site plan as determined by the City shall require a resubmission of the modified SWM site plan in accordance with this article.
A disapproved SWM site plan may be resubmitted, with the revisions addressing the City's concerns, to the City in accordance with this article. The applicable review fee must accompany a resubmission of a disapproved SWM site plan.
The City's approval of an SWM site plan authorizes the regulated activities contained in the SWM site plan for a maximum term of validity of five years following the date of approval. The City may specify a term of validity shorter than five years in the approval for any specific SWM site plan. Terms of validity shall commence on the date the City signs the approval for an SWM site plan. If an approved SWM site plan is not completed according to § 424-407 within the term of validity, then the City may consider the SWM site plan disapproved and may revoke any and all permits. SWM site plans that are considered disapproved by the City shall be resubmitted in accordance with § 424-405 of this chapter.
A. 
The developer shall be responsible for providing as-built plans of all SWM BMPs included in the approved SWM site plan. The as-built plans and an explanation of any discrepancies with the construction plans shall be submitted to the City of Hazleton Engineer's office.
B. 
The as-built submission shall include a certification of completion signed by a qualified professional verifying that all permanent SWM BMPs have been constructed according to the approved plans and specifications. If any licensed qualified professionals contributed to the construction plans, then a licensed qualified professional must sign the completion certificate.
C. 
After receipt of the completion certification by the City of Hazleton, the City Engineer or official designee may conduct a final inspection.