[Ord. No. 170-2014, 5/14/2014; as amended by Ord. No. 210-2023, 9/13/2023]
This chapter shall be known as the "Honey Brook Township Stormwater
Management Ordinance."
[Ord. No. 170-2014, 5/14/2014; as amended by Ord. No. 210-2023, 9/13/2023]
1. The governing body of the municipality finds that:
A. Inadequate management of accelerated stormwater runoff resulting
from land disturbance and development throughout a watershed increases
flooding, flows and velocities, contributes to erosion and sedimentation,
overtaxes the capacity of streams and storm sewers, greatly increases
the cost of public facilities to convey and manage stormwater, undermines
floodplain management and flood reduction efforts in upstream and
downstream communities, reduces infiltration and groundwater recharge,
increases nonpoint source pollution to waterways, and threatens public
health and safety.
B. Inadequate planning and management of stormwater runoff resulting
from land disturbance and development throughout a watershed can harm
surface water resources by changing the natural hydrologic patterns,
accelerating stream flows (which increase scour and erosion of stream
beds and stream banks, thereby elevating sedimentation), destroying
aquatic habitat, and elevating aquatic pollutant concentrations and
loadings such as sediments, nutrients, heavy metals, and pathogens.
Groundwater resources are also impacted through loss of recharge.
C. A comprehensive program of stormwater management, including minimization
of impacts of new development, redevelopment, and other earth disturbance
activities causing accelerated runoff and erosion and loss of natural
infiltration, is fundamental to the public health, safety, and general
welfare of the people of the Municipality and all of the people of
the commonwealth, their resources, and the environment.
D. Stormwater is an important water resource that provides infiltration
and groundwater recharge for water supplies and base flow of streams,
which also protects and maintains surface water quality.
E. Impacts from stormwater runoff can be minimized by reducing the volume
of stormwater generated and by using project designs that maintain
the natural hydrologic regime and sustain high water quality, infiltration,
stream base flow, and aquatic ecosystems. Cost-effective and environmentally
sensitive stormwater management can be achieved through the use of
nonstructural site design techniques that minimize impervious surfaces,
reduce disturbance of land and natural resources, avoid sensitive
areas (i.e., riparian buffers, floodplains, steep slopes, wetlands,
etc.), and consider topography and soils to maintain the natural hydrologic
regime.
F. Public education on the control of pollution from stormwater is an
essential component in successfully addressing stormwater.
G. Federal and state regulations require the Municipality to implement
a program of stormwater controls. The Municipality is required to
obtain a permit and comply with its provisions for stormwater discharges
from its separate storm sewer system under the National Pollutant
Discharge Elimination System (NPDES).
H. Nonstormwater discharges to municipal or other storm sewer systems
can contribute to pollution of the waters of the commonwealth.
I. The use of green infrastructure, low-impact development (LID), and
conservation design (CD) are intended to address the root cause of
water quality impairment by using systems and practices which use
or mimic natural processes to: 1) infiltrate and recharge, 2) evapotranspire,
and/or 3) harvest and use precipitation near where it falls to earth.
Green infrastructure practices, LID, and CD contribute to the restoration
or maintenance of predevelopment hydrology.
[Ord. No. 170-2014, 5/14/2014; as amended by Ord. No. 210-2023, 9/13/2023]
1. The purpose of this chapter is to protect public health, safety and
general welfare, property, and water quality by implementing drainage
and stormwater management practices, criteria, and provisions included
herein for land development, construction, and earth disturbance activities,
to achieve the following throughout the Municipality:
A. Reduce the frequency and magnitude of flooding and stormwater impacts
affecting people, property, infrastructure, and public services.
B. Sustain or improve the natural hydrologic characteristics and water
quality of groundwater and surface water.
C. Protect natural resources, including riparian and aquatic living
resources and habitats.
D. Maintain the natural hydrologic regime of land development sites
and their receiving watersheds.
E. Minimize land disturbance and protect and incorporate natural hydrologic
features, drainage patterns, infiltration, and flow conditions within
land development site designs.
F. Reduce and minimize the volume of stormwater generated and manage
and release stormwater as close to the source of runoff as possible.
G. Provide infiltration and maintain natural groundwater recharge to
protect groundwater supplies and stream base flows, prevent degradation
of surface water and groundwater quality, and to otherwise protect
water resources.
H. Reduce stormwater pollutant loads to protect and improve the chemical,
physical, and biological quality of groundwater and surface water.
I. Reduce scour, erosion, and sedimentation of stream channels.
J. Reduce flooding impacts and preserve and restore the natural flood-carrying
capacity of streams and their floodplains.
K. Protect adjacent and downgradient lands from adverse impacts of direct
stormwater discharges.
L. Minimize impervious surfaces and connected impervious surfaces to
promote infiltration and reduce the volume and impacts of stormwater
runoff.
M. Provide proper long-term operation and maintenance of all permanent
stormwater management facilities, BMPs and conveyances that are implemented
within the Municipality.
N. Reduce the impacts of runoff from existing developed land undergoing
redevelopment while encouraging new development and redevelopment
in urban areas and areas designated for growth.
O. Implement an illicit discharge detection and elimination program
that addresses nonstormwater discharges.
P. Provide stormwater management performance standards and design criteria
on a watershed basis.
Q. Provide standards to meet certain NPDES stormwater permit requirements.
R. Meet legal water quality requirements under state law, including
regulations at 25 Pa. Code Chapter 93, to protect, maintain, reclaim,
and restore the existing and designated uses of the waters of the
commonwealth.
S. Implement the requirements of total maximum daily load (TMDL) where
applicable to waters within or impacted by the Municipality.
T. Provide review procedures and performance standards for stormwater
planning and management.
U. Fulfill the purpose and requirements of PA Act 167 (PA Act 167, Section
3):
(1)
Encourage planning and management of stormwater runoff in each
watershed which is consistent with sound water and land use practices.
(2)
Authorize a comprehensive program of stormwater management designated
to preserve and restore the flood-carrying capacity of commonwealth
streams; to preserve to the maximum extent practicable natural stormwater
runoff regimes and natural course, current and cross-section of water
of the commonwealth; and to protect and conserve groundwaters and
groundwater recharge areas.
(3)
Encourage local administration and management of stormwater
consistent with the commonwealth's duty as trustee of natural
resources and the people's constitutional right to the preservation
of natural, economic, scenic, aesthetic, recreational and historic
values of the environment.
[Ord. No. 170-2014, 5/14/2014; as amended by Ord. No. 210-2023, 9/13/2023]
1. The Municipality is empowered or required to regulate land use activities
that affect runoff and surface water and groundwater quality and quantity
by the authority of:
A. Act of October 4, 1978, P.L. 864 (Act 167) 32 P.S. § 680.1
et seq., as amended, the "Storm Water Management Act" (hereinafter
referred to as "the Act");
B. Second Class Township Code, 53 P.S. § 65101 et seq.;
C. Act of July 31, 1968, P.L. 805, No. 247, 53 P.S. § 10101
et seq., as amended, the Pennsylvania Municipalities Planning Code,
Act 247 hereinafter referred to as the "MPC").
[Ord. No. 170-2014, 5/14/2014, as amended by Ord. No. 208-2021, 2/10/2021, and by Ord. No. 210-2023, 9/13/2023]
1. The following activities are regulated by this chapter:
A. All regulated activities as defined in this chapter, including, but
not limited to, new development, redevelopment, and earth disturbance
activities that are located within the Municipality shall be subject
to regulation by this chapter.
B. When a building and/or grading permit is required for any regulated
activity on an existing parcel or approved lot created by a subdivision
and/or improved as a land development project, issuance of the permit
shall be conditioned upon adherence to the terms of this chapter.
C. Installation of stormwater management facilities or appurtenances thereto and/or the diversion or piping of any natural or man-made stream channel, other than that associated with the activities of Subsection
1A shall be reviewed and approved by the municipality prior to commencement of construction. A limited plan and calculations, as determined by the Municipal Engineer, shall be prepared in accordance with the design criteria of this chapter and shall meet all applicable outside agency permitting requirements.
D. This chapter contains the stormwater management performance standards and design criteria that are necessary from a watershed-based perspective. The Municipality's stormwater management conveyance and system design criteria (e.g., inlet spacing, inlet type, collection system design and details, outlet structure design, etc.) shall continue to be regulated by the applicable municipal ordinance(s) and applicable state regulations, or as included in §
20-311 of this chapter.
E. All activities related to proper operation and maintenance of approved
stormwater management facilities and best management practices and
all activities that may contribute nonstormwater discharges to a municipal
separate storm sewer system or waters of the commonwealth are subject
to regulation by this Part.
2. Duty of Persons Engaged in a Regulated Activity. Notwithstanding
any provision(s) of this chapter, including exemptions, any landowner
or any person engaged in a regulated activity, including, but not
limited to, the alteration or development of land, which may affect
stormwater runoff characteristics, shall implement such measures as
are reasonably necessary to prevent injury to health, safety, or other
property. Such measures also shall include actions as are required
to manage the rate, volume, direction, and quality of resulting stormwater
runoff in a manner which otherwise adequately protects health, property,
and water quality of waters of the commonwealth.
3. Phased and Incremental Project Requirements.
A. Any regulated activity (including, but not limited to, new development,
redevelopment, or earth disturbance) that is to take place incrementally
or in phases, or occurs in sequential projects on the same parcel
or property, shall be subject to regulation by this chapter if the
regulated impervious surface or earth disturbance exceeds the corresponding
threshold for exemption (as presented in Table 20-106.1, Thresholds
for regulated activities that are exempt from the provisions of this
chapter as listed below).
B. The date of adoption of this chapter shall be the starting point
from which to consider tracts as parent tracts relative to future
subdivisions, and from which impervious surface and earth disturbance
computations shall be cumulatively considered, unless such requirements
have previously been adopted, then the earliest date of the applicable
municipal ordinance adoption shall remain as the starting point. The
starting point shall be May 15, 2014. For example: If, after adoption
of this chapter, an applicant proposes construction of a 600 square
foot garage, that project would be exempt from the requirements of
this chapter as noted in Table 20-106.1. If, at a later date, an applicant
proposes to construct a 900 square foot room addition on the same
property, the applicant would then be required to implement the stormwater
management and plan submission requirements of this chapter for the
cumulative total of 1,500 square feet of additional impervious surface
added to the property since adoption of this chapter.
[Ord. No. 170-2014, 5/14/2014, as amended by Ord. No. 202-2019, 11/13/2019, and by Ord. No. 210-2023, 9/13/2023]
1. Requirements for Exempt Activities.
A. An exemption from any requirement of this chapter shall not relieve
the applicant from implementing all other applicable requirements
of this chapter or from implementing such measures as are necessary
to protect public health, safety, and welfare, property, and water
quality.
B. An exemption shall not relieve the applicant from complying with
the requirements for state-designated special protection waters designated
by PADEP as high quality (HQ) or exceptional value (EV) waters, or
any other current or future state or municipal water quality protection
requirements.
C. An exemption under this chapter shall not relieve the applicant from
complying with all other applicable municipal ordinances or regulations.
2. General Exemptions. Regulated activities that:
A. Involve less than 1,000 square feet of regulated impervious surfaces
and less than 5,000 square feet of earth disturbance; or
B. Are listed in Subsection 2C, are exempt from those (and only those)
requirements of this chapter that are included in the sections and
articles listed in Table 20-106.1. Exemptions are for the items noted
in Table 20-106.1 only and shall not relieve the landowner from other
applicable requirements of this chapter. Exemption shall not relieve
the applicant from implementing such measures as are necessary to
protect health, safety, and welfare, property, and water quality.
Table 20-106.1
Thresholds for Regulated Activities that are Exempt from the
Provisions of this Chapter as Listed Below (see Notes below)
|
---|
Chapter Part/Section
|
Activities Listed in § 20-106, Subsection 3
|
Less than 1,000 Square Feet of Regulated Impervious Surfaces
and
Less than 5,000 Square Feet of Proposed Earth Disturbance
|
Greater Than or Equal to 1,000 Square Feet of Regulated Impervious
Surfaces
or
Greater than Equal to 5,000 Square Feet of Proposed Earth Disturbance
|
---|
Part 1
|
Not exempt
|
Not exempt
|
Not exempt
|
Part 2
|
Not exempt
|
Not exempt
|
Not exempt
|
|
Not exempt
|
Not exempt
|
Not exempt
|
|
Exempt
|
Exempt
|
Not exempt
|
Part 4
|
Exempt
|
Exempt
|
Not exempt
|
Part 5
|
Exempt
|
Exempt
|
Not exempt
|
Part 6
|
Exempt
|
Exempt
|
Not exempt
|
Part 7
|
Exempt
|
Exempt
|
Not exempt
|
Part 8
|
Not exempt
|
Not exempt
|
Not exempt
|
Part 9
|
Not exempt
|
Not exempt
|
Not exempt
|
Other erosion, sediment and pollution control requirements
|
Must comply with Title 25, Chapter 102, of the Pa. Code and
other applicable state and municipal codes, including the Clean Streams
Law.
|
NOTES:
|
---|
•
|
Specific activities listed in § 20-106, Subsection 3, are exempt from the indicated requirements, regardless of size.
|
•
|
A proposed regulated activity must be less than both the regulated
impervious surfaces and proposed earth disturbance thresholds to be
eligible for exemption from the requirements listed in this table.
|
•
|
Regulated impervious surface: As defined in this chapter.
|
•
|
Exempt: Regulated activities are exempt from the requirements
of listed section(s) only; all other provisions of this chapter apply.
These exemptions have no bearing on other municipal regulations or
ordinances.
|
•
|
Small projects (1,000 square feet to 2,000 square feet of proposed impervious surface) and agricultural projects shall refer to Table 20-106.2 and Subsections 4 and 5 for additional guidance.
|
3. Exemptions for Specific Activities. The following specific regulated activities are exempt from the requirements of §§
20-301,
20-304,
20-305,
20-306,
20-307,
20-308,
20-309, and
20-310, and Part
4, Part
5, Part
6, and Part
7) of this chapter (as shown in Table 20-106.1), unless otherwise noted below. All other conveyance and system design standards established by the Municipality in other codes or ordinances shall be required, and all other provisions of this chapter shall apply.
A. Emergency Exemption: Emergency maintenance work performed for the
protection of public health, safety, and welfare. This exemption is
limited to repair of the existing stormwater management facility;
upgrades, additions or other improvements are not exempt. A written
description of the scope and extent of any emergency work performed
shall be submitted to the Municipality within two calendar days of
the commencement of the activity. A detailed plan shall be submitted
no later than 30 days following commencement of the activity. If the
Municipality finds that the work is not an emergency, then the work
shall cease immediately, and the requirements of this chapter shall
be addressed as applicable.
B. Maintenance: Any maintenance to an existing stormwater management
facility, BMP or conveyance made in accordance with plans and specifications
approved by the Municipal Engineer or Municipality. Modifications,
including expansions, to existing stormwater management systems, facilities,
BMPs or conveyances are not exempt.
C. Existing Landscaping: Use of land for maintenance, replacement, or
enhancement of existing landscaping.
D. Gardening: Use of land for gardening for home consumption.
E. Agricultural Related Activities.
(1)
Agricultural activities (as defined in Part
2), when performed in accordance with the requirements of 25 Pa. Code Chapter 102.
(2)
Conservation practices (as defined in Part 2) that do not involve
construction of any new or expanded impervious surfaces.
(3)
High tunnel if:
(a)
The high tunnel or its flooring does not result in an impervious
surface exceeding 25% of all structures located on the landowner's
total contiguous land area, or 5,000 square feet, whichever is greater;
and
(b)
The high tunnel meets one of the following:
1)
The high tunnel is located at least 100 feet from any perennial
stream or watercourse, public road, or neighboring property line.
2)
The high tunnel is located at least 35 feet from any perennial
stream or watercourse, public road or neighboring property line and
located on land with a slope not greater than 7%.
3)
The high tunnel is supported with a buffer or diversion system
that does not directly drain into a stream or other watercourse by
managing stormwater runoff in a manner consistent with the requirements
of Pennsylvania Act 167.
F. Forest Management. Forest management operations, which are consistent with a sound forest management plan as filed with the Municipality and which comply with the Pennsylvania Department of Environmental Protection's management practices contained in its publication "Soil Erosion and Sedimentation Control Guidelines for Forestry" (as amended or replaced by subsequent guidance). Such operations are required to have an Erosion and Sedimentation Control Plan, which meets the requirements of 25 Pa. Code Chapter 102 and meets the erosion and sediment control standards of §
20-303 of this chapter.
G. Maintenance of Existing Gravel and Paved Surfaces. Replacement of existing gravel and paved surfaces shall meet the erosion and sediment control requirements of 25 Pa. Code Chapter 102 and §
20-303 of this chapter and is exempt from all other requirements of this chapter listed in §
20-106, Subsection
3, above. Resurfacing of existing gravel and paved surfaces is exempt from the requirements of this chapter listed above. Paving of existing gravel surfaces is exempt from the requirements of this chapter listed above. Construction of new or additional impervious surfaces shall comply with all requirements of this chapter as indicated in Table 20-106.1.
H. Municipal Roadway Shoulder Improvements. Shoulder improvements conducted
within the existing roadway cross-section of municipal owned roadways,
unless an NPDES permit is required, in which case the proposed work
must comply with all requirements of this chapter.
I. In-Place Replacement of Residential Dwelling Unit. The replacement
in the exact footprint of an existing one- or two-family dwelling
unit.
J. In-Place Replacement, Repair, or Maintenance of Residential Impervious
Surfaces. The replacement of existing residential patios, decks, driveways,
pools, garages, and/or sidewalks that are accessory to an existing
one- or two-family dwelling unit in the exact footprint of the existing
impervious surface.
4. Modified Requirements for Small Projects. Regulated activities that
involve 1,000 to 2,000 square feet of regulated impervious surfaces
and 10,000 square feet or less of proposed earth disturbance may apply
the modified requirements presented in the "Simplified Approach to
Stormwater Management for Small Projects" (simplified approach) (Appendix
20-A) to comply with the requirements of §§
20-301,
20-304,
20-305,
20-306,
20-307,
20-308,
20-309, and
20-310, and Part
4, Part
5, Part
6 and Part
7 of this chapter (as shown in Table 20-106.2). The applicant shall first contact the Municipal Engineer: to confirm that the proposed project is eligible for use of the simplified approach and is not otherwise exempt from these chapter provisions; to determine what components of the proposed project are to be considered as impervious surfaces; and to determine if other known site or local conditions exist that may preclude the use of any techniques included in the simplified approach. Appendix 20-A includes instructions and procedures for preparation, submittal, review, and approval of documents required when using the simplified approach and shall be adhered to by the applicant. Infiltration testing for projects using the simplified approach is recommended but is not required by this chapter. All other provisions of this chapter shall apply.
Table 20-106.2
Thresholds for Regulated Activities that are Eligible for "Modified"
Requirements for the Provisions of this Chapter that are Listed Below
|
---|
Chapter Part/Section
|
Activities Listed in § 20-106, Subsections 4 and 5
|
---|
Part 1
|
All provisions apply
|
Part 2
|
All provisions apply
|
|
All provisions apply
|
|
Exempt if modified requirements of § 20-106, Subsections 4 and/or 5 are applied
|
Part 4
|
Exempt if modified requirements of § 20-106, Subsections 4 and/or 5 are applied
|
Part 5
|
Exempt if modified requirements of § 20-106, Subsections 4 and/or 5 are applied
|
Part 6
|
All provisions apply
|
Part 7
|
Exempt if modified requirements of § 20-106, Subsections 4 and/or 5 are applied
|
Part 8
|
All provisions apply
|
Part 9
|
All provisions apply
|
Other erosion, sediment and pollution control requirements
|
Must comply with Title 25, Chapter 102, of the Pa. Code and
other applicable state and municipal codes, including the Clean Streams
Law.
|
NOTES:
|
---|
•
|
Modified Requirements: Regulated activities listed within the sections of this chapter noted in Table 20-106.2 are eligible for exemption only from the indicated sections and subsections of this chapter and only if the modified requirements of § 20-106, Subsection 4 and 5 are met to the satisfaction of the Municipality; all other provisions of this chapter apply.
|
5. Modified Requirements for Agricultural Structures. It is the declared policy of the commonwealth to conserve and protect and to encourage the development and improvement of its agricultural lands for the production of food and other agricultural products. Municipalities must encourage the continuity, development, and viability of agricultural operations within its jurisdiction. Except as necessary to protect the public health, safety and welfare, regulated activities involving proposed new or expanded impervious surfaces associated with agricultural activities are exempt from the requirements of §§
20-301,
20-304,
20-305,
20-306,
20-307,
20-308,
20-309, and
20-310, and Part
4, Part
5, Part
6 and Part
7 of this chapter (and listed in Table 20-106.2) only when it has been demonstrated to the satisfaction of the Municipality that the proposed project will comply with all of the requirements listed below. The applicant shall first contact the Municipal Engineer: to confirm that the proposed project is eligible for use of the "Simplified Approach to Stormwater Management for Agricultural Projects" (Appendix 20-B) and is not otherwise exempt from these chapter provisions;
to determine what components of the proposed project are to be considered
as impervious surfaces; and to determine if other known site or local
conditions exist that may preclude the use of any techniques included
in the simplified approach. Appendix 20-B includes instructions and
procedures for preparation, submittal, review, and approval of documents
required when using the simplified approach and shall be adhered to
by the applicant. Infiltration testing for projects using the simplified
approach is recommended but is not required by this chapter. All other
provisions of this chapter shall apply. To be eligible for exemption
from the chapter provisions stated above and consideration of use
of the simplified approach in Appendix 20-B, the proposed regulated
activity shall:
A. Be directly associated with an agricultural activity (as defined
in Part 2);
B. Include less than 15,000 square feet of proposed new or expanded
impervious surface and adjoining vehicle parking and movement area;
C. Be installed on a farm or mushroom operation that has a current Mushroom Farm Environmental Management Plan (MFEMP) reviewed and deemed adequate by the Conservation District, or an agricultural erosion and sediment control plan or conservation plan (as defined in Part
2) that complies with the requirements of 25 Pa. Code Chapter 102;
D. Divert runoff from the proposed new or expanded impervious surfaces
(including vehicle parking and movement area) entirely away from animal
management, waste management and crop farming areas and any other
source of pollutants;
E. Include BMP(s) that will permanently retain at least one inch of
rainfall runoff from the total area of proposed new or expanded impervious
surfaces and vehicle parking and movement areas;
F. Be designed so that any point of discharge of runoff from the proposed
new or expanded impervious surface (excluding vehicle movement area):
(1)
Is not directly connected to, and is not directly connected
to any constructed conveyance that is connected to, a municipal separate
storm sewer system or public roadway;
(2)
Is located at least 150 feet from any municipal separate storm
sewer system or public roadway, or any constructed conveyance connected
to any municipal separate storm sewer system or public roadway.
G. Either:
(1)
Have all proposed new or expanded impervious surfaces and proposed
vehicle parking and movement areas and BMP(s) included within the
current MFEMP or current agricultural erosion and sediment control
plan or a conservation plan for the farm or mushroom operation; or
(2)
Be constructed per design plans prepared and sealed by a licensed
professional in conformance with the PADEP "Best Practices for Environmental
Protection in the Mushroom Farm Community" (2003 or as amended), or
per design plans prepared and sealed by a licensed professional (or
Conservation District staff person designated by NRCS) that comply
with USDA NRCS standards and specifications, and for which completion
of construction will be certified by the licensed (or NRCS-designated
design) professional responsible for the design; and
H. Not be eligible for exemption if an NPDES permit is required.
[Ord. No. 170-2014, 5/14/2014; as amended by Ord. No. 210-2023, 9/13/2023]
1. Approvals issued and actions taken pursuant to this chapter do not
relieve the applicant of the responsibility to secure and comply with
other required permits or approvals for activities regulated by any
other applicable code, rule, act, law, regulation, or ordinance.
2. To the extent that this chapter imposes more rigorous or stringent
requirements for stormwater management than any other code, rule,
act, law, regulation or ordinance, the specific requirements contained
in this chapter shall take precedence.
3. Nothing in this chapter shall be construed to affect any of the Municipality's
requirements regarding stormwater matters that do not conflict with
the provisions of this chapter, such as local stormwater management
design criteria (e.g., inlet spacing, inlet type, collection system
design and details, outlet structure design, etc.). The requirements
of this chapter shall supersede any conflicting requirements in other
municipal ordinances or regulations.
[Ord. No. 170-2014, 5/14/2014; as amended by Ord. No. 210-2023, 9/13/2023]
1. For all activities requiring submittal of a stormwater management
(SWM) site plan that involve subdivision or land development, the
applicant shall post financial security to the Municipality for the
timely installation and proper construction of all stormwater management
facilities as required by the approved SWM site plan and this chapter,
and such financial security shall:
A. Be equal to or greater than the full construction cost of the required
facilities except to the extent that financial security for the cost
of any of such improvements is required to be and is posted with the
Pennsylvania Department of Transportation in connection with a highway
occupancy permit application; and
B. Be determined, collected, applied, and enforced in accordance with
Sections 509 – 511 of the MPC and the provisions of the Municipality's subdivision and land development ordinance (SALDO) (Chapter
22 of this Code).
2. For all activities requiring submittal of a stormwater management
(SWM) site plan, that is not part of a subdivision or land development
application and do not meet the requirements to utilize the simplified
approaches for small projects or agricultural projects, the applicant
shall post a financial security (bond, letter of credit or cash) to
the municipality for the timely installation and proper construction
of all stormwater management facilities as required by the approved
SWM site plan and this chapter, and such financial security shall
be equal to 110% of the cost of the required facilities except to
the extent that financial security for the cost of any of such improvements
is required to be and is posted with the Pennsylvania Department of
Transportation in connection with a highway occupancy permit application.
A. In the event that any SWM facilities which may be required have not
been installed as provided in the approved SWM site plan the Honey
Brook Township Board of Supervisors is hereby granted the power to
enforce any corporate bond, or other security by appropriate legal
and equitable remedies. If proceeds of such bond, or other security
are insufficient to pay the cost of installing or making repairs or
corrections to all the SWM facilities covered by said security, the
Honey Brook Township Board of Supervisors may, at its option, install
part of such SWM facilities and may institute appropriate legal or
equitable action to recover the monies necessary to complete the remainder
of the SWM facilities. All of the proceeds, whether resulting from
the security or from any legal or equitable action brought against
the developer, or both, shall be used solely for the installation
of the SWM facilities covered by such security, and not for any other
municipal purpose.
[Ord. No. 170-2014, 5/14/2014; as amended by Ord. No. 210-2023, 9/13/2023]
1. General. The requirements of this chapter are essential and shall be strictly adhered to. For any regulated activity where, after a close evaluation of alternative site designs, it proves to be impracticable to meet any one or more of the mandatory minimum standards of this chapter on the site, the Municipality may approve measures other than those in this chapter, subject to §
20-109, Subsections
2 and
3.
2. The governing body shall have the authority to waive or modify the
requirements of one or more provisions of this chapter if the literal
enforcement will exact undue hardship because of peculiar conditions
pertaining to the land in question, provided that such modification
will not be contrary to the public interest and that the purpose and
intent of the chapter is observed. Cost or financial burden shall
not be considered a hardship. Modification may also be considered
if an alternative standard or approach can be demonstrated to provide
equal or better achievement of the results intended by the chapter.
A request for modification shall be in writing and accompany the SWM
site plan submission. The request shall state in full the grounds
and facts on which the request is based, the provision or provisions
of the chapter involved and the minimum modification necessary.
3. PADEP Approval Required. No waiver or modification of any regulated
stormwater activity involving earth disturbance greater than or equal
to one acre may be granted by the Municipality unless that action
is approved in advance by PADEP or the Chester County Conservation
District.
[Ord. No. 170-2014, 5/14/2014; as amended by Ord. No. 210-2023, 9/13/2023]
Any permit or authorization issued or approved based on false,
misleading, or erroneous information provided by an applicant is void
without the necessity of any proceedings for revocation. Any work
undertaken or use established pursuant to such permit or other authorization
is unlawful. No action may be taken by a board, agency, or employee
of the Municipality purporting to validate such a violation.