[Ord. No. 170-2014, 5/14/2014; as amended by Ord. No. 210-2023, 9/13/2023]
1.
For any regulated activity, unless exempt per the provisions of § 20-106:
A.
Preparation and implementation of an approved SWM site plan is required.
B.
No regulated activity shall commence until the Municipality issues written approval of a SWM site plan, which demonstrates compliance with the requirements of this chapter and, if required, a letter of adequacy has been issued by the Conservation District for an erosion and sediment control plan.
C.
The preliminary or final approval of subdivision and/or land development plans, and the issuance of any building or occupancy permit shall not proceed until the applicant has received written approval of a SWM site plan from the Municipality.
D.
The SWM site plan approved by the Municipality shall be on site throughout the duration of the regulated activity.