A.
Persons proposing subdivisions or developments requiring a main extension for water service shall prepare applications described in this section with the necessary supporting documents. The policy of the Township is to permit extensions only when paid for and installed by the applicant. No facilities for supply, treatment, storage, transmission or distribution of water within the service area of the Township shall be constructed unless the Township shall give its consent and the Township Engineer shall approve construction plans and specifications therefore.
B.
It is the policy of the Township to charge connection fees for connection to its water system following the rates set forth in the Township's Rate Schedule. The connection fee is charged per service unit.
C.
Unless otherwise approved where locations do not front on a street or easement with a water main, residential subdivisions containing three or more building sites or lots or any residential structure to be used by three or more families, regardless of volume of flow, and all nonresidential developments such as schools, commercial buildings, industrial buildings and other structures will be required to install a water system to be connected with the nearest existing water mains in the Township.
D.
For residential subdivisions not fronting on a street or easement with a water main and containing two or less building sites or lots, or if the lands are deemed by the Township to be too remote from any existing facilities, consideration will be given to an individual well or approved alternative in lieu of connection to existing facilities.
E.
Any main extension and related facilities installed under the provisions of this section, or easement required for the purpose, shall be transferred to the Township as hereinafter described.
F.
During construction but before final acceptance, the Township shall have the right to use any completed portion of the system without waiving its right to further inspection or testing or to order correction of any defects provided the Township does not unreasonably delay inspection, testing and acceptance of that portion of the system.
G.
Use of the water system for any unauthorized or unapproved use(s) shall not be permitted.
H.
Easements will be required for water mains and other facilities not located within an existing public right-of-way. The width of such easements will be determined by the Township, depending on the size and depth of main or other facilities to be located in the easement. Easements must be extended to the nearest adjacent property if future service will be required.
I.
Easement documents must be in a form acceptable to the Township, and must incorporate the following language:
(1)
No fill, material, machinery, appliances, or similar objects may be placed on the said premises which will impose an additional loading in excess of 100 pounds per square inch without the prior written approval of the Township. Provided; however, that nothing contained herein shall be deemed to limit the ability of grantors to use the land over the easement for the storage of vehicles.