A.
All construction of water system facilities shall be under the jurisdiction of the Township, either directly, or through inspectors under the supervision of the Township Engineer.
(1)
The Township Engineer and the applicant's engineer shall enforce compliance with the approved plans and specifications.
(2)
The Township Engineer shall have the work discontinued in the event of noncompliance.
(3)
The applicant shall furnish the name of the occupant, the street address, and lot and block number to the Township at least two weeks prior to a request for the certificate of occupancy from the Construction Code Official to assure that the water system inspection has been accomplished, and all fees have been paid.
(4)
No water service connections shall be made to the appropriate street main whether tested or not unless under the supervision and inspection of the representative for the Township. Curb stop installations are subject to review and approval by the licensed operator prior to the issuance of a certificate of occupancy.
B.
A valve shall be installed at each connection to an existing main and shall remain closed until permission is received from the Township to open same. This permission will not be granted until each section of the section has been cleaned, disinfected and flushed, sampled, tested and approved by the Township.