The following are the specific proposed plans for the 95 acres within the specific plan:
A. 
Land Use Within Specific Plan – North.
1. 
The northern specific plan east of Yucca Ridge Road includes 38 single-family residential lots of a minimum 20,000 square feet, served by an internal "loop" street with access to Yucca Ridge Road and Barranca Avenue.
2. 
The northern specific plan west of Yucca Ridge Road includes 12 single-family residential lots of a minimum 20,000 square feet, served by a cul-de-sac street with access to Yucca Ridge Road.
B. 
Land Use Within Specific Plan – South.
1. 
The southern specific plan includes 74 single-family residential lots of a minimum 20,000 square feet, served by an extension of Baldy Vista Avenue that proceeds south then east to Barranca Avenue.
2. 
The design accounts for access provisions concerning a private agreement that the Monrovia Nursery property owners made regarding the Fairmount Cemetery.
3. 
A private drive will serve a residence north of Fairmount Cemetery and five new residential lots of at least 20,000 square feet.
4. 
A linear park along the Burlington Northern Santa Fe Railroad right-of-way has been included. The park includes a trail; an extension of the trail in place east of Barranca Avenue within the Arboreta planned community.
5. 
A stormwater detention facility in the southwest corner of the Specific Plan is proposed, replacing the existing Citrus basin.
Figure 3: Existing Zoning and General Plan Designations
 Title 21--Image-380.tif
(Ord. 1944 §§ 1, 2 (Exh. A), 2011)
The specific plan area is currently zoned for, and designated as detached single-family residential and will remain as such.
A. 
Zoning. Although the actual zoning for the specific plan area will be "SP" (specific plan), development will adhere to the provisions of the specific plan and also use the city of Glendora's E-7 20,000 zoning district standards as a guide. The specific plan requires minimum 20,000 square foot lots.
B. 
General Plan. The specific plan is in conformance with and consistent with the general plan maintaining the properties' current low-density residential designation (1-3 du/ac).
Figure 4: Proposed Circulation
 Title 21--Image-381.tif
(Ord. 1944 §§ 1, 2 (Exh. A), 2011)
A. 
Project Access—Circulation—Street Improvements. As shown in Figure 4, several new streets and street extensions are proposed in the specific plan. Street designs for all proposed new streets and street extensions are shown in Figures 6 through 9.
1. 
Within the Specific Plan – North.
a. 
Loop Street. An internal "loop" street serves the northern specific plan area east of Yucca Ridge Road with access to Yucca Ridge Road and Barranca Avenue.
b. 
Cul-de-Sac. A cul-de-sac street serves the northern specific plan west of Yucca Ridge Road with access to Yucca Ridge Road.
c. 
No Direct Connection to Sierra Madre. No new road has a direct connection to Sierra Madre Avenue.
d. 
Calera Drive Unextended. Calera Avenue remains unextended, with the exception that lockable decorative bollards will allow emergency access to the northern specific plan through the existing terminus of Calera Avenue.
2. 
Within the Specific Plan – South.
a. 
Baldy Avenue Extension. The southern specific plan area will be served by an extension of Baldy Vista Avenue that will extend south then east to Barranca Avenue.
b. 
Street Network. A street connecting to Barranca Avenue is proposed that reaches the border with Azusa, but does not cross the boundary. Four streets link to this street, creating a network that serves specific plan - south.
c. 
Private Drive. A private drive serves five lots and an existing home and provides access to Fairmount Cemetery.
Figure 5: Sierra Madre Avenue Improvement
 Title 21--Image-382.tif
d. 
Traffic Signal. The purpose of the signal is to allow a u-turn movement at the intersection enabling residents to have access to the site from the south-bound leg of Barranca. No left turn into the site is allowed from northbound Barranca because the proximity of the railroad track to the project entry makes the left turn unsafe in the event of vehicle queuing to make the left. But it also does provide the means of access to the linear park but this is a secondary purpose.
B. 
Emergency Access Points. Four emergency access points are located in Figure 4, Proposed Circulation, and detailed designs of each are shown in Figures 10 through 13.
C. 
Sierra Madre Avenue Widening. Sierra Madre Avenue is an important and popular route that forms the northern edge of the specific plan. It serves as a critical circulation element for automobiles and should serve as a safe and convenient pedestrian route, as well. However, in its current state Sierra Madre Avenue has, effectively, no pedestrian or bicycle facilities. The right-of-way consists of a narrow two-lane road with nearly no shoulders and a severe drop-off without any sidewalks, curbs, barriers or landscaping.
The specific plan calls for retaining the northern edge of pavement but regrading and widening the roadbed, adding an 8-foot on-street parking lane on the north and potentially, curb and gutter. Further to the south is a 12-foot westbound travel lane, a 12-foot center turn lane, and a 12-foot eastbound travel lane, and a 14-foot-wide landscape area with a sidewalk/trail and up to a 6-foot high masonry theme wall consistent with the delineation of existing subdivisions east of the specific plan area.
D. 
The Closure of Milton Drive. The specific plan shall provide for a closure of Milton Drive substantially in compliance with Exhibit A (see Appendix 6), and subject to the approval of the County of Los Angeles. The City Engineer shall have the authority to determine substantial compliance. If the County of Los Angeles does not approve closure of Milton Drive, traffic calming measures shall be constructed on Milton Drive, substantially in compliance with Exhibit B and C (see Appendix 6). The City Engineer shall have the authority to determine substantial compliance.
Figure 6: Street Design—Sierra Madre Avenue
 Title 21--Image-383.tif
Figure 7: Street Design—Streets "C," "D" (North) and Streets "A" (South) and Baldy Vista Avenue
 Title 21--Image-384.tif
Figure 8: Street Design—Streets "A, B, E, F, G" (North) and "B, C, D, E, F, G"(South) and West Danton Drive
 Title 21--Image-385.tif
Figure 9: Street Design—Private Drive
 Title 21--Image-386.tif
Figure 10: Emergency Access—Calera Avenue
 Title 21--Image-387.tif
Figure 11: Emergency Access—Citrus Avenue/Monrovia Lane
 Title 21--Image-388.tif
Figure 12: Emergency Access—West Danton Drive
 Title 21--Image-389.tif
Figure 13: Emergency Access—Oakbank Drive
 Title 21--Image-390.tif
Figure 14: Linear Park Concept
 Title 21--Image-391.tif
Figure 15: Linear Park Cross Sections "A-A," "B-B"
 Title 21--Image-392.tif
Figure 16: Linear Park Cross Section "C-C"
 Title 21--Image-393.tif
E. 
Linear Park/Linear Sidewalk. A linear park is proposed to be located at the southern extreme of the specific plan adjacent to the Burlington Northern Santa Fe Railroad right-of-way. The park serves as a continuation of the existing park and trail created with the Arboreta planned community (see the Arboreta specific plan) east of Barranca Avenue. A portion of the park functions as a water quality facility by incorporating drainage swales. The park includes a decorative fence separating the park from the railroad right-of-way.
(Ord. 1944 §§ 1, 2 (Exh. A), 2011)
A. 
Grading Plan and Grading Cross Sections. Grading is to conform to the final geotechnical report as part of the approval process of any subdivision or parcel map and applicable local grading regulations. The Monrovia Nursery property has been used as a commercial nursery for several decades and has been graded for that purpose. This specific plan transforms this land into two residential lot subdivisions with minimum 20,000 square-foot parcels; this will require new grading which will conform to this specific plan.
1. 
The northern specific plan generally slopes to the south at an approximate grade of 10% with an approximate 65-foot elevation change across the site which is only 600 feet wide. The site is bound to the north by Sierra Madre Avenue, Barranca Avenue to the east, and existing residential lots to the south and west. To accommodate this grade difference within the project site, the grading plan has been sensitive to grade transitions to avoid the feel of new structures "towering" over the existing residences. The site is kept at an elevation below Sierra Madre to help diminish the vertical difference across the site and will also allow the residences on the north side of Sierra Madre to continue to enjoy their views to the south. The slopes in this area are kept at an approximate maximum height of 25 feet to help reduce the vertical difference to the existing residences to the south and between proposed residences in this new subdivision.
Figure 17: Grading Plan
 Title 21--Image-394.tif
2. 
The southern specific plan slopes generally to the southwest. The low point of the site is at the corner of Citrus Avenue and the existing Burlington Northern Santa Fe Railroad (the southwest corner of the specific plan). As such, the project's detention basin is located here. The grading of this southern site is dominated by the existing edge conditions, as the site is adjacent to existing residences to the north, east, and west, and the existing BNSF Railroad to the south. The proposed grading of this area reduces the size of the slopes between the new and existing residences to better blend the site into the neighborhood while also balancing the site.
3. 
The Fairmount Cemetery is surrounded by the specific plan. In response, the plan maintains access to, and includes a landscape buffer around, the historic cemetery.
4. 
A private street is included to the highest point of the southern project site, north of the Fairmount Cemetery to access five (minimum 20,000 square foot) lots and to provide access to the existing residence on top of the hill at 1326 Sierra Madre Avenue. This private street will not exceed a maximum grade of 15%.
5. 
To insure that all existing facilities, utilities and easements are taken into account, and that the grading is within appropriate guidelines for all agencies affected by the project, the developer's engineer shall submit the grading plans to all affected agencies for review and approval prior to the issuance of a grading permit from the city of Glendora.
B. 
Grading Plan Development Standards.
1. 
All grading must be in substantial conformance with the overall conceptual grading plan, the Uniform Building Code, Chapter 70, and city of Glendora standards and ordinances.
2. 
Prior to any development within any area of the specific plan, an overall conceptual grading plan for the portion in process shall be submitted for planning department approval as required. The grading plan for each area shall be used as a guideline for subsequent detailed grading plans for individual stages of development within that area, and shall include preliminary pad and roadway elevations.
3. 
Unless otherwise approved by the city of Glendora, all cut and fill slopes shall be constructed at inclinations of no steeper than 2 horizontal feet to 1 vertical foot.
4. 
A grading permit shall be obtained from city of Glendora, prior to grading.
5. 
Grading activity shall comply with South Coast Air Quality Management District, Rule 403.
6. 
Erosion control practices shall be implemented during grading activities.
7. 
The grading contractor shall be required to obtain an encroachment permit from any agency or city prior to entering any public rights-of-way.
8. 
All construction activities, including clearing, grading, or excavation that results in the disturbance of at least one acre total land area, or activity which is part of a larger common plan of development of one acre or greater shall obtain the appropriate National Pollutant Discharge Elimination System (NPDES) construction permit and pay the appropriate fees. All development within the specific plan boundaries shall be subject to future requirements adopted by the city of Glendora to implement the NPDES program.
Figure 18: North Cross Sections "A-A," "B-B"
 Title 21--Image-395.tif
Figure 19: South Cross Sections "C-C," "D-D," "E-E"
 Title 21--Image-396.tif
(Ord. 1944 §§ 1, 2 (Exh. A), 2011; Ord. 1965 § 2, 2012)
The specific plan has addressed several key issues related to drainage and water quality design requirements. The proposed drainage plan will help alleviate existing flooding concerns, adequately convey proposed stormwater runoff within proposed storm drain systems, and will include the use of existing and proposed detention facilities on-site and off-site to reduce peak runoff rates to levels equal to or less than pre-project levels and below the design capacity of the downstream storm drain system. The proposed water quality plan for stormwater runoff will help reduce the transport of urban pollutants that may occur on-site towards downstream receiving waters. Following are descriptions of the project area hydrology, detention, hydraulics, and water quality.
A. 
Hydrology. A preliminary drain, detention and SUSMP Analysis for Monrovia Nursery Project-Glendora Portion August 11, 2010 (Preliminary Drainage Report) for the specific plan has been prepared to analyze the hydrologic impacts of development for the north and south portions of the city of Glendora Monrovia Nursery project area. The Monrovia Nursery property was previously comprised of nearly 600 acres that extended across the city of Azusa and city of Glendora. A portion of the property was sold in recent years for the development of the city of Azusa portion, leaving the city of Glendora portion as a separate development project. This is an important consideration as both portions share the same overall watershed that is tributary through the project area and share an outfall location at the southwest corner of the specific plan, referred to as the 1264 Drain, located at the intersection of the existing railroad and Citrus Avenue which is maintained by Los Angeles County.
The preliminary hydrology for the specific plan includes a comprehensive analysis of the overall watershed, including both the city of Azusa and city of Glendora project areas that are tributary to the 1264 Drain. For the specific plan, the existing condition is considered the proposed condition from the city of Azusa project, with the north and south portions of the Glendora project undeveloped. The proposed condition for the Glendora project models the north and south portions as developed, and uses a proposed storm drain alignment that conveys flows from the north to the south within Baldy Vista Avenue to the southwest corner of the project into a proposed detention facility, referred to as Facility G1.
B. 
Detention/Detention Basins. The following list identifies the names and locations of existing and proposed detention basins that are relevant to the specific plan. (See Figure 20, Stormwater Plan, for locations.)
Figure 20: Stormwater Plan
 Title 21--Image-397.tif
1. 
Facility 2B (Existing). Located just west of West Leadora Avenue, on the city of Azusa side of the city boundary line. It was constructed as part of the Azusa project and was designed to discharge less than 40 cubic feet per second (cfs).
There are no physical modifications proposed for Detention Basin 2B. The northwest portion of the project will continue to drain through Detention Basin 2B. Due to the development, the amount of runoff entering and exiting the basin will increase compared to existing conditions, however, the design for 2B accounted for the future developed condition of this area. Therefore, the maximum water surface elevation (WSEL) will remain within the basin and the maximum outflow will remain within the 40 cfs design criteria originally intended for the facility as a part of the adjacent city of Azusa.
2. 
Facility 4D (Existing). Located further south along the city boundary line, and southwest of Fairmount Cemetery, this detention basin straddles the municipal boundary, existing within both the city of Azusa, and the city of Glendora.
Figure 21: Watershed
 Title 21--Image-398.tif
The specific plan proposes that the Glendora portion of Detention Facility 4D be filled, fulfilling an agreement between the city of Azusa and the city of Glendora. Then Glendora runoff is to be redirected to proposed Detention Facility G1. Detention Basin 4D would, therefore, experience a significant decrease in tributary area, a slight increase in the maximum WSEL for a 50-year design storm, and a significant decrease in maximum outflow into the existing storm drain system in Citrus Avenue. The increase in the maximum WSEL is acceptable since the maximum WSEL remains well below the top of basin elevation.
3. 
Facility G1 (Proposed). Proposed to be located at the southwest corner of the specific plan and intended to replace the Glendora portion of Facility 4D. It would be installed near the northeast corner of the Citrus Avenue and existing Burlington Northern Santa Fe Railroad intersection.
Detention Basin G1 will be constructed as part of the specific plan and would receive runoff from a majority of the north and south portions of the specific plan, the tributary watershed north of Sierra Madre Avenue that will be conveyed through the specific plan, and from the existing neighborhood located between the north and south specific plan.
The resulting discharge rate at Outfall 2C (approximately 620 cfs), into Los Angeles County department of public works 1264 Drain (78-inch reinforced concrete pipe), will be less than the approved post-project flow rates in the approved August 2005 report prepared for the adjacent city of Azusa project, and significantly less than the approved design discharge flow rate of 920 cfs for the 1264 Drain (also identified in the August 2005 report).
Figure 22: Facility G-1
 Title 21--Image-399.tif
C. 
Hydraulics—Storm Drain. There are existing drainage problems, as addressed in the Preliminary Drainage Report dated August 11, 2010 (i.e., flooding concerns) identified within the specific plan. Proposed drainage improvements should help alleviate these issues and adequately convey runoff through the specific plan to the downstream storm drain facility (at the southwest corner of the project site). The proposed improvements will be sized to convey off-site flows received from the north (entering the site from Sierra Madre Avenue at two separate locations), from the west (entering the site from one existing detention basin, while the other existing detention basin is routed down Citrus Avenue within the city of Azusa project limits), and on-site flows from throughout the specific plan and surrounding neighborhood (both existing and proposed residential streets and lots).
The exact alignment of the main storm drain segments is subject to minor adjustment in final engineering; however, the storm drain systems will run towards the southwest corner and ultimately discharge to the Los Angeles County Department of Public Works facility (1264 Drain – 78-inch reinforced concrete pipe). A preliminary layout for the proposed storm drain system and existing storm drain systems to remain in place are shown in Figure 20, Stormwater Plan.
D. 
Water Quality—Permanent Stormwater BMPs.
1. 
In the city of Glendora, water quality treatment solutions are to use infiltration, extended detention, or retention based solutions. For large single-family lots, requirements include installing an infiltration trench or bioretention area on each single-family lot, sized to infiltrate 0.75 inches from the lot. Each lot will utilize one of these methods (or combination thereof) to satisfy the water quality treatment requirements; however, the newly created streets also require treatment. Among the solutions for stormwater will include one of the following (or an approved equivalent):
a. 
Vegetated swales with infiltration (where feasible);
b. 
Bioretention areas adjacent to inlet locations;
c. 
Proprietary systems such as Filterra or Modular Wetland at each inlet location.
The bottom portion of Detention Basin G-1 will be used for infiltration or extended detention (water quality benefits), limited to streets in close proximity to the basin.
2. 
Pursuant to Low Impact Development (LID) requirements, each lot in the specific plan will be required to utilize site design Best Management Practices (BMP) directing impervious areas to pervious areas (i.e., roof drains to landscaping), and street runoff will be directed to vegetated areas as well, where feasible. Therefore, water quality treatment, LID, and EPI requirements will be met with a variety of permanent stormwater BMP solutions. For portions of the streets where it is not feasible to direct runoff to natural vegetated areas, then proprietary bioretention systems may be utilized that will provide contact time with soil and vegetation for water quality storm events.
3. 
The following summarizes the preliminary solutions proposed for water quality and LID/EPI requirements:
a. 
Lots. Infiltration trench and/or bioretention raingarden.
b. 
Streets.
i. 
Vegetated swales with bioretention or infiltration trench;
ii. 
Bioretention system(s) at curb inlet locations;
iii. 
Soft bottom detention basin with bioretention/infiltration.
4. 
Each of the above systems will be numerically sized to detain, retain, or infiltrate the first 0.75 inches of stormwater runoff where feasible, with remaining areas numerically sized to treat 0.75 inches or a comparable treatment flow rate (cfs), such as bioretention systems at inlet locations. Preliminary locations of these facilities are shown in Figure 23, Water Quality Plan.
Figure 23: Water Quality Plan
 Title 21--Image-400.tif
5. 
These permanent stormwater BMPs located on lots will be maintained by the private landowner or an established homeowner's association; the permanent BMPs installed for treatment of public street runoff will be maintained by the city of Glendora. In the case of the soft bottom detention basin, the Los Angeles County department of public works/Los Angeles County flood control district will assume operation and maintenance responsibilities, upon its acceptance into the Los Angeles County flood control district.
(Ord. 1944 §§ 1, 2 (Exh. A), 2011)
The specific plan consists of detached single-family residences on parcels of at least 20,000 square feet, affording every homeowner with a significant private open space within their own lot. Therefore public open space was not a driving emphasis of the plan. However, open space is still important to engender a sense of shared experience and community, especially open space that contains amenities to encourage pedestrian and bicycle circulation. This specific plan proposes several open space facilities that demonstrate an appreciation for the history of the area, and foster neighborhood interaction.
A. 
Linear Park. The specific plan includes a linear park adjacent to the Burlington Northern Santa Fe Railroad that include facilities similar to those already in place in the linear park east of Barranca Avenue, including a trail/sidewalk, a noise attenuation wall, stormwater facilities, and landscaping.
B. 
Linear Sidewalk. Throughout the specific plan non-contiguous sidewalks are to be installed concurrent with new development. These sidewalks will be separated from the street with a landscaped parkway. Of particular significance are the new sidewalks proposed within the Linear Park and the meandering sidewalk on the south side of the improved Sierra Madre Avenue.
C. 
Fairmount Cemetery. Fairmount Cemetery is an important and revered local historic landmark. The specific plan recognizes this and provides a landscape buffer as well as some design details that help parking for special events.
D. 
Homeowner's Association Lots. Slopes adjacent to some residences, emergency access points and gateways will be landscaped and maintained by the homeowner's association. The precise specifics of such will be made a part of subsequent covenants, conditions and restrictions.
(Ord. 1944 §§ 1, 2 (Exh. A), 2011)
Baldy Vista Creek is an open drainage channel which outlets onto the specific plan area and the Covina Canal is in an existing water pipe line that will need to be removed and relocated. The flow in Baldy Vista Creek will be placed in a pipe as it enters the specific plan area. Easements are proposed to address these elements as well as nonutility matters such as the Fairmount Cemetery and a new private drive easement to an existing homesite at 1326 West Sierra Madre Avenue.
A. 
1326 West Sierra Madre Avenue. The specific plan anticipates a provision for an access easement for a private drive to reach the property at 1326 West Sierra Madre Avenue because the current access route to this property would be eliminated as part of the implementation of the specific plan.
B. 
Fairmount Cemetery. The specific plan includes a buffer for Fairmount Cemetery and provides on-street and off-street parking opportunities for services at the cemetery and maintenance purposes.
C. 
Covina Canal. The Covina Canal within the specific plan is a below grade facility in a 42-inch ductile iron pipe, though it is partially exposed at the southern end of Baldy Vista Creek. The specific plan proposes removing and relocating the pipe. New easements associated with this action will follow. Prior to recordation of the final map, the subdivider will be required to obtain the necessary quitclaim deed from the Covina Irrigating Company (CICO) vacating the easement.
D. 
Los Angeles County Department of Public Works. The Los Angeles County department of public works is responsible for operations and maintenance of sewers within the specific plan, a series of easements related to sewer lines within the specific plan have been incorporated into the utility plans.
Figure 24: Covina Canal Realignment
 Title 21--Image-401.tif
Figure 25: Baldy Vista Creek 2009 Photos
 Title 21--Image-402.tif
(Ord. 1944 §§ 1, 2 (Exh. A), 2011)
A. 
The specific plan's water supply is provided by the city of Glendora. The Los Angeles County sanitation district provides the sanitary sewer service. The water and sewer system plan is based on the existing capacity of water and sewer facilities surrounding the project. The city of Glendora draws 222 acre-feet per year from the Covina irrigating canal.
1. 
The following water facilities exist in the vicinity of the project:
Existing 8″ Ductile Iron Pipe in Sierra Madre Avenue
Existing 20″ Ductile Iron Pipe in Sierra Madre Avenue
Existing 30″ Ductile Iron Pipe in Sierra Madre Avenue
Existing 8″ in Yucca Ridge Road
Existing 30″ in Yucca Ridge Road (High pressure Transmission Main)
Existing 6″ in Foxglove Court
Existing 6″ in Leadora Avenue
Existing 30″ in Leadora Avenue (High pressure Transmission Main)
Existing 6″ in Donington Street
Existing 6″ in Calera Avenue
Existing 6″ in Baldy Vista Avenue
Existing 6″ in Milton Drive
Existing 6″ in Oakbank Drive
Existing 6″ in Danton Drive
Existing 8″ in Barranca Avenue
2. 
The following sewer facilities exist in the vicinity of the project:
Existing 8″ Sewer in Yucca Ridge Road
Existing 8″ Sewer in Sierra Madre Avenue
Existing 8″ Sewer in Leadora Avenue
Existing 8″ Sewer in Calera Avenue
Existing 8″ Sewer in Donington Street
Existing 8″ Sewer in Baldy Vista Avenue
Existing 8″ Sewer in Milton Drive
Existing 8″ Sewer in Danton Drive
Existing 8″ Sewer Southerly along the Existing Covina Canal Alignment, from West Danton Drive to Oakbank Drive
Existing 8″ Sewer in Oakbank Drive
Existing 8″ Sewer in Barranca Avenue from Leadora Avenue to Milton Drive
B. 
Water System.
1. 
The city of Glendora provides water to customers from three sources:
a. 
Groundwater from the San Gabriel Valley Water District (SGVWD).
b. 
Surface water from the Metropolitan Water District of Southern California (MWD) through the Three Valleys Municipal Water District.
c. 
Surface water from the Covina Irrigating Company (CIC) by way of the Covina Canal (42-inch ductile iron pipe). The water is disinfected with chlorine or chloramines before it is delivered to the customer.
2. 
City water lines exist throughout the specific plan. The specific plan - north is proposed to obtain service from the existing 8-inch water lines on Yucca Ridge Road and Barranca Avenue. The specific plan - south is proposed to obtain service from the 6-inch existing water lines on Baldy Vista Avenue, Milton Drive, West Danton Drive, Oakbank Drive and the existing 8-inch water lines on Barranca Avenue. The domestic water system will be designed and constructed per city of Glendora standards.
3. 
The domestic potable water system for the entire specific plan will also be used for fire protection of the site. The domestic potable water system will include the fire hydrant system and any necessary fire protection services to insure adequate fire safety for the specific plan. A hydraulic analysis may be required to determine adequacy of the existing 6-inch and 8-inch water lines to serve the project, in which case upsizing of these existing water lines may be required to ensure adequate water pressure to the proposed residential homes.
Figure 26: Water Plan
 Title 21--Image-403.tif
C. 
Sewer System.
1. 
The specific plan is comprised of a total of 95 acres, 35 acres are part of the specific plan - north and 60 acres are part of the specific plan - south. The sanitation district of Los Angeles County provides wastewater management of the city of Glendora. The city of Glendora is located in sanitation district No. 22, which operates the San Jose Creek reclamation plant in the city of Industry.
2. 
The specific plan - north wastewater is conveyed to a low point on Street "B" at which point it drains southerly through a sewer easement and connects to the existing local 8-inch sewer line on Calera Avenue. From this point the 8-inch line flows in Baldy Vista Avenue southerly to Danton Drive where it connects to the existing sewer outfall.
3. 
In the specific plan - south, sewer on West Danton Drive will be extended to proposed Street "E," and the flows will be conveyed southerly to proposed Street "A." The proposed sewer alignment will continue westerly along Street "A" through a proposed sewer easement along the proposed detention basin (Lot M). The proposed sewer will continue southerly under the Burlington Northern Santa Fe Railroad and connect to an existing 8-inch sewer on Citrus Avenue and Foothill Boulevard. A jack and bore process will be needed to extend the sewer under the Burlington Northern Santa Fe Railroad. In anticipation of the development of the property the Monrovia Nursery company obtained an agreement for a sewer easement through an adjoining property located at 1155 West Foothills Boulevard. The sewer line would require coordination, review and approval from the Southern California Regional Rail Authority.
4. 
For the proposed residential lots draining to the existing sewer on Oakbank Drive the sewer will be extended westerly from the existing sewer stub on Milton Drive and Oakbank Drive to the proposed Street "N" cul-de-sac. Wastewater then flows through an existing 8-inch sewer pipeline that crosses under the existing Burlington Northern Santa Fe Railroad along the Oakbank Drive alignment.
5. 
To determine the peak flow generated from the project site, the following design criteria were used. Generation factors in the 2006 Sewer Master Plan are based on acreage.
a. 
The factor shown on Table 1 was used to determine flows. The factor is based on five dwelling units per acre and medium low-density residential flow factor from the 2006 sewer master plan.
b. 
Table 2 provides the calculated project sewer flows. A peaking factor of 1.66 was used to be consistent with the highest diurnal peaking factor of the 2006 sewer master plan.
TABLE 1
LAND USE
FACTOR (gpd)
UNITS
Residential
250
Per dwelling unit
TABLE 2
LAND USE
UNITS
FACTOR (gpd)
UNIT
AVG. FLOW (gpd)
PEAK FLOW (gpd)1
PEAK FLOW (gpd)2
PEAK FLOW (cfs)
Residential
129*
250
du
32.637
37
56
0.1241
Notes:
*
Currently 124 residential units are proposed. Sewer flow calculation based on September 18, 2007 report prepared by RBF.
1
Based on residential peak factor =1.66 per 2006 sewer master plan.
2
Based on inflow and infiltration factor of 50% average daily flow per 2006 sewer master plan.
6. 
The specific plan's wastewater is ultimately conveyed to the existing JOH unit 8-L relief line located on Baseline Avenue south of the project and this leads to the San Jose Creek reclamation plant. The size of the relief trunk line is 24 inches to 30 inches and has a capacity of 20 to 30 cfs. In the beginning of 2009 the relief trunk line was measured at 4 to 6 cfs peak flow, and therefore currently has the capacity to serve the specific plan.
D. 
Water and Sewer Development Standards.
1. 
All water facilities will be designed and constructed in accordance with the city of Glendora Standards and the Standard Specifications for Public Works Construction, 2009 edition (Green Book).
2. 
All sewer facilities will be designed and constructed in accordance with the sanitation district of Los Angeles County and the Standard Specifications for Public Works Construction, 2009 edition (Green Book).
3. 
Final engineering for domestic water and sewer facilities shall be subject to the appropriate studies to confirm the alignment and capacity of new or existing lines to serve new development from the project. The city engineer shall set the criteria used in preparing the studies and shall also review and approve the studies.
Figure 27: Sewer Plan
 Title 21--Image-404.tif
(Ord. 1944 §§ 1, 2 (Exh. A), 2011)
A. 
Utility Plan. The specific plan - north and south is surrounded on the north, west, and east by existing development served by Southern California Edison for electricity and the gas company for natural gas. While portions of the specific plan have electrical service, the gas service does not currently exist. Nonetheless, both utilities exist in the roadways and property surrounding the nursery.
B. 
Electrical. The existing locations of the electrical facilities are illustrated on the following page. All of the existing facilities are located above ground. In the specific plan - north, electrical facilities are located on the east side of Yucca Ridge Road north of Sierra Madre Avenue, west side of Barranca Avenue and along the southern property boundary. In the specific plan - south, overhead electrical facilities enter the nursery property south of the Burlington Northern Santa Fe Railroad tracks between Calvary Lutheran Church and the Autumn Oaks condominiums. The facilities extend north through the southern portion of the site into residential areas northeast of the Fairmount Cemetery. Overhead lines are also located throughout much of the northern perimeter of the specific plan - south between the property and existing residences. In general, overhead service is provided to the rear of the adjacent residential properties. It is anticipated that implementation of the specific plan will require coordination with Southern California Edison to extend electrical service into the proposed specific plan. All new electrical service within the specific plan must be underground. The developer will need to coordinate with the city and Southern California Edison to identify existing poles and wires that may need to be relocated to implement the specific plan.
C. 
Natural Gas. The existing locations of the natural gas facilities are illustrated in Figure 28, Gas and Electric Utility Plan. No natural gas facilities are located in the specific plan, however, natural gas facilities exist in almost all the surrounding streets including: Sierra Madre Avenue, Barranca Avenue, Yucca Ridge Road, Donington Street, Calera Avenue, Leadora Avenue, Oakbank Drive, Baldy Vista Avenue, West and East Danton Drive. It is anticipated that implementation of the specific plan will require coordination with the gas company to extend natural gas service into the proposed specific plan.
Figure 28: Gas and Electric Utility Plan
 Title 21--Image-405.tif
(Ord. 1944 §§ 1, 2 (Exh. A), 2011)