All storm drainage improvements shall be constructed in accordance
with the Woodbridge Road Specifications on file in the Office of the
Commission. The storm drainage system proposed for a subdivision shall
be designed by the applicant's engineer and shall be accompanied by
a narrative report. The design shall take into account the total drainage
area of which the subdivision is a part and the required pipe size(s)
for the drainage system to serve the area. The construction of the
drainage system to serve the proposed subdivision shall be the responsibility
of the subdivider.
All subdivision improvements to be dedicated to the Town shall
be inspected by the Board of Selectmen or such agent and at such times
as may be designated by the Board of Selectmen in accordance with
the Woodbridge Road Specifications on file in the Office of the Commission.
Monuments shall be placed at all lot corners, at angle points,
and the points of curves in roads and at such intermediate points
as may be necessary. The location of all monuments shall be indicated
on the subdivision plan. They shall be installed by the subdivider
and their accuracy certified by a licensed land surveyor. The monuments
shall be made of concrete, and shall be 36 inches in length. The top
shall be four inches square and a point cast into it. The base shall
be six inches square. The monument shall be set with the top six inches
above finished grade.
The developer must certify to the Commission through a licensed
land surveyor that monuments have been installed in compliance with
the subdivision plan. No bond release shall be made until this certification
is received by the Commission.
Where a proposed road or storm drain joins a state highway or
state drain, the applicant shall obtain a permit for such connection
from the Department of Transportation and shall present a copy of
such permit to the Commission with the application. The applicant
shall have furnished the Department of Transportation with a copy
of the proposed subdivision plan of improvements, and said copy, with
appropriate notations by the Department of Transportation, shall accompany
the permit.
The following steps are required before a road will be accepted
by the Town:
A. Approval of the proposed layout by the Commission and the Board of
Selectmen and the posting of a Performance Bond therefor.
B. Construction of the road in compliance with the Woodbridge Road Specifications.
C. Application to the Commission by the subdivider for i) the release of the completion bond in compliance with §
490-9 of this chapter and ii) the preliminary acceptance for routine maintenance of the road by the Board of Selectmen for a period of not less than one year.
D. Approval of above-referred-to application by the Commission and the
Board of Selectmen and the posting of a maintenance bond.
E. Repair by the subdivider to the satisfaction of the Board of Selectmen
of any deficiencies which become apparent during the preliminary maintenance
period.
F. Application to the Commission by the subdivider for i) the release of the maintenance bond in compliance with §
490-11A of this chapter and ii) the final acceptance of the road by the Board of Selectmen into the Town highway system.
G. Approval of above-referred-to application by the Commission and the
Board of Selectmen and acceptance of the road into the Town highway
system.