(a)
Period of Validity. The period of validity for a Conditional Use Permit or a Planned Development Permit shall begin on the permit's effective date as set forth in Section 12-35.109. The period of validity shall run pursuant to subsection (c) of this section. The expiration date of a discretionary permit issued in conjunction with a tentative subdivision map shall correspond with the expiration of that map, including any extensions.
(b)
Establishment. A conditional use permit or planned development permit shall be deemed established if the following actions occur within three years of the effective date of the approval or within such other time period designated by the approval:
(1)
In the case of a conditional use permit or planned development permit where ministerial permits are required, such permits have been issued.
(2)
In the case of a conditional use permit or planned development permit where no ministerial permits are required, the use authorized by the permit has been established. In circumstances where a business license is required, such business license has been issued.
(c)
Expiration. A conditional use permit or planned development permit shall expire and be of no further force or effect if:
(1)
The permit is not established within three years of the permit's effective date or such other time period designated by the permit approval, by state law or by this code; or
(2)
After establishment, the use or activity for which the permit was approved is discontinued or abandoned for a period of six months.
(d)
Time Extensions.
(1)
Upon application before expiration of the period of validity, the original decision-making body may grant an extension to the period of validity for up to two years if it finds that there has been adequate due diligence to implement and complete the permit, or that there are significant economic factors that justify additional time. The filing of an application for extension shall stay expiration of the permit until action is taken on the time extension by the decision-making body.
(2)
Projects not requiring a time extension may be constructed in accordance with the requirements and standards in effect at the time of permit approval provided the construction complies with all project conditions of approval and all laws in effect at the time of the permit approval. However, any project or permit requiring a time extension shall conform to the requirements and standards in effect at the time the extension is granted.
(Ord. 2019-04 § 1, eff. 7/4/19; Ord. 2024-03, eff. 5/2/2024)