(a)
After approval by the planning and zoning commission of the
site plan, architectural plan, and landscaping plan, the developer
shall, within twelve (12) months thereafter, submit to the city three
(3) copies, one (1) electronic copy, and one (1) mylar copy of the
final site plan and the final landscaping plan. At the same time,
three (3) copies of the final construction plans for the development
shall be submitted to the city and three (3) copies of the final construction
plans to the city engineer.
(b)
In the event that the developer does not submit final plans
within the twelve (12) months, the plans approved by the planning
and zoning commission shall be considered as being void and must be
resubmitted to planning and zoning commission along with payment of
all appropriate fees.
(c)
After acceptance of the final plans by the city council, one
(1) set each of the final site plan, the final landscaping plan, and
the construction plans shall be returned to the developer signed by
the city engineer and the mayor for the city council that the plans
are approved for construction.
(d)
All final plans shall be in strict accordance with those approved
by the planning and zoning commission including all conditions of
approval. It shall be unlawful to issue a building permit prior to
final approval of the site plan and landscaping plan by city council.
As to proposed development located in the VC district, it shall further
be unlawful to issue a building permit prior to approval of final
construction plans by the city council.
(1995 Code, sec. 9-150; Ordinance 2024-03-00998 adopted 3/21/2024)