[Ord. No. 1238, 9/7/2022]
1. For all regulated activities, unless preparation of an SWM site plan
is specifically exempted in Section 302:
A. Preparation and implementation of an approved SWM site plan is required.
B. No regulated activities shall commence until the Borough issues written approval of an SWM site plan, which demonstrates compliance with the requirements of this Chapter
21A.
2. SWM site plans approved by the Borough, in accordance with § 406,
shall be on site throughout the duration of the regulated activity.
3. The Borough may, after consultation with DEP, approve measures for meeting the state water quality requirements other than those in this Chapter
21A, provided that they meet the minimum requirements of, and do not conflict with, state law, including, but not limited to, the Pennsylvania Clean Streams Law.
4. For all regulated earth disturbance activities, erosion and sediment control BMPs shall be designed, implemented, operated, and maintained during the regulated earth disturbance activities (e.g., during construction) to meet the purposes and requirements of this Chapter
21A and to meet all requirements under Title 25 of the Pennsylvania Code and the Pennsylvania Clean Streams Law. Various BMPs and their design standards are listed in
the Erosion and Sediment Pollution Control Program Manual (E&S
Manual), No. 363-2134-008, as amended and updated (see § 901).
5. Impervious Areas.
A. The measurement of impervious areas shall include all of the impervious
areas in the total proposed development even if development is to
take place in stages.
B. For development taking place in stages, the entire development plan must be used in determining conformance with this Chapter
21A.
C. For projects that add impervious area to a parcel, the total impervious area on the parcel is subject to the requirements of this Chapter
21A; except that the volume controls in § 303 and the peak rate controls of § 304 do not need to be retrofitted to existing impervious areas that are not being altered by the proposed regulated activity.
6. Stormwater flows onto adjacent property shall not be created, increased, decreased, relocated, or otherwise altered without written notification to the adjacent property owner(s). Such stormwater flows shall be subject to the requirements of this Chapter
21A.
7. All regulated activities shall include such measures as necessary
to:
A. Protect health, safety, and property.
B. Meet the water quality goals of this Chapter
21A by implementing measures to:
(1)
Minimize disturbance to floodplains, wetlands, and wooded areas.
(2)
Maintain or extend riparian buffers.
(3)
Avoid erosive flow conditions in natural flow pathways.
(4)
Minimize thermal impacts to waters of this Commonwealth.
(5)
Disconnect impervious surfaces by directing runoff to pervious
areas, wherever possible.
C. Incorporate methods described in the Pennsylvania Stormwater Best
Management Practices Manual (BMP Manual) (see § 901).
8. The design of all facilities over karst shall include an evaluation
of measures to minimize adverse effects.
9. Infiltration BMPs should be spread out, made as shallow as practicable, and located to maximize use of natural on-site infiltration features while still meeting the other requirements of this Chapter
21A.
10. Normally dry, open top, storage facilities should completely drain
both the volume control and rate control capacities over a period
of time not less than 24 and not more than 72 hours from the end of
the design storm.
11. The design storm volumes to be used in the analysis of peak rates
of discharge should be obtained from the latest version of the Precipitation-Frequency
Atlas of the United States, National Oceanic and Atmospheric Administration
(NOAA), National Weather Service, Hydrometeorological Design Studies
Center, Silver Spring, Maryland. NOAA's Atlas 14 can be accessed
at:
http://hdsc.nws.noaa.gov/hdsc/pfds (see § 901).
12. For all regulated activities, SWM BMPs shall be designed, implemented, operated, and maintained to meet the purposes and requirements of this Chapter
21A and to meet all requirements under Title 25 of the Pennsylvania Code, the Pennsylvania Clean Streams Law, and the Pennsylvania Storm Water Management Act.
13. Various BMPs and their design standards are listed in the BMP Manual
(see § 901).
[Ord. No. 1238, 9/7/2022]
1. Regulated activities that result in cumulative earth disturbances less than one acre are exempt from the requirements in §§ 303, 304, and Part
4 of this Chapter
21A.
2. Agricultural activity is exempt from the SWM site plan preparation requirements of this Chapter
21A provided the activities are performed according to the requirements of 25 Pa. Code, Chapter 102.
3. Forest management and timber operations are exempt from the SWM site plan preparation requirements of this Chapter
21A provided the activities are performed according to the requirements of 25 Pa. Code, Chapter 102.
4. Exemptions from any provisions of this Chapter
21A shall not relieve the applicant from the requirements in § 301, Subsections
4 through 11.
5. The Borough may deny or revoke any exemption pursuant to this section
at any time for any project that the Borough believes may pose a threat
to public health and safety or the environment.
[Ord. No. 1238, 9/7/2022]
The green infrastructure and low impact development practices provided in the BMP Manual shall be utilized for all regulated activities wherever possible. Water volume controls shall be implemented using the Design Storm Method in Subsection 1 or the Simplified Method in Subsection 2, below. For regulated activity areas equal or less than one acre that do not require hydrologic routing to design the stormwater facilities, this Chapter
21A establishes no preference for either methodology; therefore, the applicant may select either methodology on the basis of economic considerations, the intrinsic limitations on applicability of the analytical procedures associated with each methodology, and other factors.
1. The Design Storm Method (CG-1 in the BMP Manual) is applicable to
any size of regulated activity (see § 901). This method
requires detailed modeling based on site conditions.
A. Do not increase the post-development total runoff volume for all
storms equal to or less than the two-year twenty-four-hour duration
precipitation.
B. For modeling purposes:
(1)
Existing (predevelopment) nonforested pervious areas must be
considered meadow in good condition.
(2)
Twenty percent of existing impervious area, when present, shall
be considered meadow in good condition in the model for existing conditions.
2. The Simplified Method (CG-2 in the BMP Manual) provided below is
independent of site conditions and should be used if the Design Storm
Method is not followed (see § 901). This method is not applicable
to regulated activities greater than one acre or for projects that
require design of stormwater storage facilities. For new impervious
surfaces:
A. Stormwater facilities shall capture at least the first two inches
of runoff from all new impervious surfaces.
B. At least the first one inch of runoff from new impervious surfaces
shall be permanently removed from the runoff flow, i.e., it shall
not be released into the surface waters of this Commonwealth. Removal
options include reuse, evaporation, transpiration, and infiltration.
C. Wherever possible, infiltration facilities should be designed to
accommodate infiltration of the entire permanently removed runoff;
however, in all cases at least the first 0.5 inch of the permanently
removed runoff should be infiltrated.
D. This method is exempt from the requirements of § 304, Rate
Controls.
[Ord. No. 1238, 9/7/2022]
1. For areas not covered by a release rate map from an approved Act
167 Stormwater Management Plan:
Post-development discharge rates shall not exceed the pre-development
discharge rates for the one-, two-, five-, ten-, twenty-five-, fifty-,
and 100-year, twenty-four-hour storm events. If it is shown that the
peak rates of discharge indicated by the post-development analysis
are less than or equal to the peak rates of discharge indicated by
the pre-development analysis for one-, two-, five-, ten-, twenty-five-,
fifty-, and 100-year, twenty-four-hour storms, then the requirements
of this section have been met. Otherwise, the applicant shall provide
additional controls as necessary to satisfy the peak rate of discharge
requirement.
2. For areas covered by a release rate map from an approved Act 167
Stormwater Management Plan:
For the one-, two-, five-, ten-, twenty-five-, fifty-, and 100-year,
twenty-four-hour storm events, the post-development peak discharge
rates will follow the applicable approved release rate maps. For any
areas not shown on the release rate maps, the post-development discharge
rates shall not exceed the pre-development discharge rates.