A.
With submittal of the application for final plan approval, the subdivider shall provide one of the following performance guarantees for an amount adequate to cover the total construction costs of all required improvements in the current phase, taking into account the time span of the construction schedule and the inflation rate for construction costs:
(1)
A certified check payable to the Town or a savings account or certificate of deposit naming the Town as owner, for the establishment of an escrow account; or
(2)
The applicant may agree to a condition of approval that no lots will be sold and no building permits issued until all required improvements in the current phase have been constructed.
B.
The conditions of the performance guarantee shall be determined by the Board with the advice of the Town Engineer, Road Commissioner, and municipal officers.