[Ord. No. 24-13956, 5-20-2024]
A.
Post-Construction — Flood Control.
1.
Purpose. A development's stormwater drainage system shall be designed to:
2.
Plans And Calculations.
a.
A drainage map shall be developed from a base reproduction of the site plan or grading plan. The existing and proposed contours shall be shown, normally at two-foot intervals, for the subject property, extending off-site one hundred (100) feet or less as determined by the Engineering Department for proper design of the proposed improvements. Contour intervals other than the above shall be used as determined by the site topography. Only United State Geological Survey datum shall be used. Locations and elevations of bench mark references are available from the Engineering Department.
b.
The location of existing and proposed property lines, streets, sinkholes, railroads, areas within the tract subject to inundation by stormwater and other significant natural features, such as wooded areas and rock formations, etc., shall be included on the map. All existing and proposed stormwater facilities, such as inlets, manholes, pipes, culverts, bridges, channels, etc., and all existing and proposed improvements required for proper design review, such as pavement, buildings, etc., shall be included on the map.
c.
The runoff details shall be required, showing individual flows for each existing and proposed structure and cumulative flows in pipes and gutters, including "Q" and area. The map shall show all bodies of water, such as ponds or lakes (including surface area and elevation) and all waterways (including their names or the names of creeks or rivers they flow into).
d.
Lots shall be laid out so as to provide positive drainage away from all buildings. Individual lot drainage shall be shown and coordinated with the drainage pattern for the area and designed so that runoff from one (1) lot will not adversely affect an adjoining lot. All necessary grading to direct stormwater runoff shall be located within a drainage easement.
e.
All computations, plans and specifications related to the implementation of this Section must be prepared and sealed by a professional engineer registered in the State of Missouri.
f.
Elevation versus discharge relationship for the basin.
g.
Elevation versus storage relationship for the basin.
h.
Inflow calculations and data for all required frequencies.
i.
Hydraulic grade line computations for pipes entering and leaving the basin for all required frequencies.
j.
Site plan with two-foot contours showing land to be developed and adjoining land whose topography may affect the layout or drainage of a basin site and the location of streams and other runoff channels.
k.
Basic information regarding the receiving watercourse and affected downstream structures to a distance of two hundred (200) feet from the site. Additional analysis of the receiving stream of greater distances from the site shall be performed if required by the City Engineer.
l.
A summary of routing calculations for all required frequencies.
m.
All computations, plans and specifications related to the implementation of this Section must be prepared and sealed by a professional engineer registered in the State of Missouri.
3.
Design Criteria.
a.
Projects shall be designed to detain on-site or off-site as approved and released at a rate not to exceed the allowable release rates for the 2-year, 10-year, and 100-year, 24-hour events.
b.
The 2-year, 10-year, and 100-year, 24-hour inflow hydrographs shall be determined by using Technical Release 55 (TR-55), "Urban Hydrology for Small Watersheds" from the Natural Resources Conservation Service, formerly Soil Conservation Service (SCS). The inflow hydrograph shall be developed based on the actual flow and timing characteristics upstream of the detention facility. The Rational Method for calculating stormwater runoff may be used for watersheds up to ten (10) acres.
c.
The rainfall distribution shall be Type II. The rainfall quantities to be used are from NOAA's National Weather Service, Atlas 14 Point Precipitation Frequency Estimate, and shall be as follows: three and twenty-nine hundredths (3.29) inches for the 2-year, 24-hour storm, four and eighty-two hundredths (4.82) inches for the 10-year, 24-hour storm, and seven and niney-four hundredths (7.94) inches for the 100-year, 24-hour storm.
d.
The volume of detention may be provided through permanent detention facilities such as dry basins or ponds, permanent ponds or lakes, underground storage facilities or in parking lots. It is noted that when runoff volume reduction BMPs are utilized within the tributary area upstream of a flood volume detention basin, the quantified runoff reduction may be used to adjust tributary area TR55 Curve Numbers (CN) for detention basin sizing.
e.
The engineer shall make every effort to locate the detention facility at or near the lowest point of the project such that all of the on-site runoff will be directed into the detention facility.
f.
Flows from off-site, upstream areas should be bypassed around the detention facility to ensure that the proposed detention facility will function as designed and will provide effective control of downstream flows with development in place. If off-site flows are directed into a detention facility, the allowable release rates shall not be modified without City Engineer approval. Modifying the release rate to accommodate off-site flows may reduce or eliminate the effectiveness of the detention facility, because it will no longer control the increased volume of runoff during the critical time period of the watershed.
g.
Detention basin volume will be based on routing the post-developed 2-year, 10-year, and 100-year, 24-hour inflow hydrographs through the detention facility while satisfying the appropriate allowable release rate. The routing computations shall be based on an application of the continuity principle, (i.e., level pool routing).
4.
Calculation Of Runoff.
a.
The method of calculating and routing stormwater runoff shall be as stated herein. The drainage area shall consider all on- and off-site lands contributing to the proposed development's drainage system. Capacity for such facilities shall be based on the maximum potential water shed development permitted by the Zoning Ordinance, Chapter 400.
b.
Either the Rational Method or the TR-55 Method for calculating stormwater runoff may be used for watersheds up to ten (10) acres.
c.
Figures A (rainfall intensity - referenced above) and B (runoff factors) shall be utilized with the Rational Method.[1]
[1]
Editor's Note: Figures A and B are included as attachments to this Chapter.
d.
For watersheds larger than ten (10) acres, the SCS TR-55 Method shall be utilized. Other methods to determine peak runoff must be approved by the City Engineer prior to acceptance.
e.
The minimum percentage of imperviousness to be used in design shall be based on the zoning district as shown in the following table:
Zoning District | Minimum Percentage Impervious |
|---|---|
Pre-developed | 5% |
R-1A Single-Family | 45% |
R-1B Single-Family | 50% |
R-1C Single-Family Attached | 50% |
R-1D Single-Family | 50% |
R-2 Two-Family | 60% |
R-3 Multiple-Family | 70% |
C-1 Limited Commercial | 85% |
C-2 General Commercial | 85% |
C-3 Central Commercial | 90% |
M-1 Industrial | 90% |
M-2 Industrial | 90% |
PD Planned Development Districts | TBD based on plan type |
Parking, streets, roofs | 100% |
f.
The minimum percentage of imperviousness for Planned Development Districts shall be dictated by the development plan proposed for the specific district.
g.
Special uses, such as schools, churches, etc., shall have the differential runoff computed and approved by the City Engineer.
h.
Special circumstances may dictate that the developed impervious area may differ from that shown in the above table. An example may be single-family lots of larger than ten thousand (10,000) square feet. Calculations prepared by a registered professional engineer may be submitted to the City Engineer for his/her evaluation to determine if a minimum impervious area which differs from that shown in the above table may be utilized. Likewise, the City Engineer may determine that the percent of impervious area for a particular development differs from that shown in the above table.
i.
See Figure B[2] for the runoff factor to be utilized for various impervious conditions and rainfall durations.
[2]
Editor's Note: Figure B is included as an attachment to this Chapter.
5.
Inlets. Calculations shall be submitted to demonstrate the capacity of all inlets. Such calculations must consider the cross-slope of the pavement, depth of water at the curb face, size of opening and the longitudinal grade of street. Street inlets and inlets in parking areas shall reduce the spread and depth of flow to acceptable levels during the 10-year design storm. The acceptable level of flow for a minor access or local access street would maintain an eight-foot travel lane with a maximum one-inch depth. One (1) clear ten-foot travel lane must be maintained for a collector street, and two (2) clear ten-foot travel lanes must be maintained for a major street. Any area inundated by water ponding at an inlet during the 10-year storm event shall be located within an easement or right-of-way. The effects of the 100-year storm event shall also be analyzed to ensure no property damage or dangerous conditions result. Inlets located on continuous grades may be designed to permit a portion of flow to bypass the structure; however, calculations for the downstream structure must consider the bypass.