(a) 
The following provisions apply solely to natural gas transmission pipelines 30 inches or larger interior diameter, built on or after the date of final passage of this article ("Natural Gas Transmission Pipelines" or "Pipelines") and any entities that may operate such pipelines shall be identified herein as "pipeline operators."
(b) 
As determined in the sole, but reasonable discretion of the city, natural gas transmission pipelines shall be located so that they do not interfere with or damage existing utilities, including, but not limited to, water, sewer, or gas lines, storm drains, electric lines or the facilities of any public utilities located in public rights-of-way, utility easements, municipal utility easements or other city-owned property or in private residential areas.
(c) 
The pipeline operator shall be required to comply with pipeline permit requirements in section 8-253 below and all regulations regarding noise in section 8-254 below.
(d) 
The pipeline operator shall be responsible to grade, level and restore the property affected by pipeline construction to the same surface condition, as nearly practicable, as existed before operations were first commenced within 30 days after completion of the pipeline.
(e) 
The city has control of roadways and facilities and/or lines existing within public rights-of-way, utility easements or on/under city owned property within the city, whether current or planned and the pipeline operator shall, unless pre-empted by state or federal law, design and build all natural gas transmission pipelines that will be on, over, under, along, across, within, or crossing public roads and/or all facilities and/or lines existing within the public rights-of-way, utility easements or on/under city owned property within the city limits shall be a minimum depth of 13 feet from top of pipe to surface, irrespective of the angle such pipeline crosses such roads and/or all facilities and/or other lines existing within such rights-of-way, utility easements or on/under city owned property. "Planned roadways" include but are not limited to roads shown on approved preliminary plats, approved final plats, roads shown on CAMPO maps and any roadways shown on the City of Kyle's Comprehensive Plan and/or Transportation Plan. Planned roadways may include corridors. "Planned infrastructure" includes but is not limited to water/wastewater/stormwater lines shown on approved preliminary plats, approved final plats, shown on the City of Kyle's Comprehensive Plan, Master Plans, and/or Capital Improvement Plan.
(f) 
At least 60 days prior to finalization of any natural gas transmission pipeline construction plans, the pipeline operator and/or contractor shall provide the city with the construction plans for all pipeline construction within the city to ensure that all current and future planned roadways have the pipeline designed to the above-referenced depth.
(g) 
At least ten days prior to the commencement of any pipeline construction, the pipeline operator shall give written mailed notice to all residents, tenants and property owners that are located adjacent to the proposed pipeline. The mailing shall include the pipeline operator's publication on natural gas transmission pipeline safety.
(h) 
At the time the required natural gas transmission pipeline records are submitted to the Railroad Commission of Texas, the pipeline operator shall provide the city the following information, including GPS information sufficient to locate the pipelines in the future, including the beginning and end points of the pipeline and sufficient points in between the pipeline route and the depth of cover information. This information shall be submitted to the city in a format compatible with the city's own GIS system.
(1) 
As-built or record drawings of the natural gas transmission pipelines. Accuracy of the record drawings shall meet the city requirements as established by the city engineer. The scale of the record drawings shall be a minimum of one inch to 40 feet. The drawings shall also be supplied in a DFF digital file format with the location tied to at least one nearby GPS (global positioning system) city monument. If the new pipeline length exceeds 1,000 feet within the city, the pipeline shall be tied to at least two GPS city monuments;
(2) 
The origin point and the destination of the natural gas transmission pipeline;
(3) 
Confirmation of the substance to be transported;
(4) 
A copy of the substance material safety data sheet (MSDS);
(5) 
Engineering plans, drawings and/or maps with summarized specifications showing the horizontal location, covering depths and location of shutoff valves of the subject natural gas transmission pipeline. Drawings shall show the location of other pipelines and utilities that are crossed or paralleled within 15 feet of the natural gas transmission pipeline right-of-way;
(6) 
Detailed cross-section drawings for all public rights-of-way and utility easement crossings on city property as permitted by the city; and
(7) 
A list of the names and mailing addresses of all the property owners, residents and tenants adjacent to the natural gas transmission pipeline construction.
(i) 
At the time of permitting and each year thereafter that the natural gas transmission pipeline remains active, each pipeline operator shall provide to the fire marshal and the chief of police the names, mailing addresses and telephone numbers of at least two primary persons, officers or contacts available on a 24-hour basis and at least two alternative persons, officers or contacts to be reached in the event that the primary contacts are unavailable who:
(1) 
Can initiate appropriate actions to respond to an emergency;
(2) 
Have access to information on the location of the closest shutoff valve to any specific point in the city; and
(3) 
Can furnish the common name of the material then being carried by the pipeline.
Any change in the above information must be provided to the city by contacting the city engineer prior to such change.
(j) 
Each pipeline operator shall file a copy of all initial or follow-up reports provided to the U.S. Department of Transportation or the Railroad Commission of Texas on unsafe pipeline conditions, pipeline emergencies or pipeline incidents within the city concurrently with the city. In addition, such pipeline operator shall file any initial or follow-up reports filed with state and federal environmental regulatory agencies pertaining to natural gas transmission pipeline releases within the city concurrently with the city.
(Ordinance 1041, § 1(Exh. A), adopted 7/2/2019; Ordinance 1055, § 2(Exh. A), adopted 9/9/2019; Ordinance 1091, § 2(Exh. A), 4/21/2020; Ordinance 1136, § 2(Exh. A), adopted 2/23/2021)
(a) 
In this section:
(1) 
Hazardous pipeline means a pipeline designed for the transmission of a hazardous liquid with an inside diameter of eight inches or more.
(2) 
Hazardous liquid means a liquid that is dangerous to human health or safety or the environment if used incorrectly or if not properly stored or contained. Pipeline safety regulations identify petroleum, petroleum products, or anhydrous ammonia as hazardous liquids. (Reference 49 CFR 195.2.)
(3) 
Natural gas means natural gas, the principal constituent of which is methane. For purposes of this article, natural gas is not a hazardous liquid.
(4) 
Transmission pipeline means large lines (greater than 30 inches interior diameter) that move natural gas long distances around the country, often at high pressures (typically 200—1500 psi)
(5) 
New construction means the construction after August 31, 2019, of a building intended for human occupancy and includes the construction of a new building, the construction of an addition to an existing building and the reconstruction of a portion of an existing building. The term excludes an addition to or the reconstruction or replacement of a building existing on August 31, 2019, used for:
a. 
Single-family residential use;
b. 
Small lot single-family residential use;
c. 
Single-family attached residential use;
d. 
Duplex residential use;
e. 
Two-family residential use;
f. 
Mobile home residential use; or
g. 
In a neighborhood plan combining district:
h. 
Cottage special use;
i. 
Urban home special use; or
j. 
Secondary apartment special use.
(6) 
Restricted pipeline area includes an area within 25 feet of a hazardous pipeline or within 200 feet of a natural gas transmission pipeline.
(7) 
Use requiring evacuation assistance includes the following uses:
a. 
Congregate living;
b. 
Convalescent services;
c. 
Detention facilities;
d. 
Day care services (commercial);
e. 
Hospital (general);
f. 
Hospital (limited);
g. 
Medical offices exceeding 5,000 square feet of gross floor area;
h. 
Private primary educational facilities;
i. 
Private secondary educational facilities;
j. 
Public primary educational facilities;
k. 
Public secondary educational facilities; and
l. 
Retirement housing (large site).
(b) 
Areas involving a use requiring evacuation assistance.
(1) 
Subject to subsection (b) below, a use requiring evacuation assistance is prohibited in a building intended for human occupancy that is located within 500 feet of a hazardous pipeline or within 500 feet of a natural gas transmission pipeline.
(2) 
This prohibition does not apply to a building that is located between 200 and 500 feet of a hazardous pipeline or a natural gas transmission pipeline if by resolution the council determines, after receiving a recommendation from the fire chief that:
a. 
The building has a performance-based design that provides an adequate time period for occupant evacuation to a safe place in the event of a pipeline leak or fire associated with the pipeline, after considering:
1. 
The requirements of Chapter 25-12, Article 7 (Uniform Fire Code ) and the 2000 edition of the National Fire Protection Association 101 Life Safety Code;
2. 
The site and building design;
3. 
The building's materials;
4. 
The building's distance from the pipeline;
5. 
The use of radiant energy barriers;
6. 
Access to the site and the structure by emergency responders;
7. 
Available on-site resources for emergency responders;
8. 
The topography and other natural features;
9. 
The use of the structure; and
10. 
The evacuation capability of the occupants;
b. 
The building incorporates a system for the early detection and notification of a pipeline leak, if the fire chief determines that an appropriate system is commercially available; and
c. 
The performance-based design for occupant evacuation and the early detection and notification system are certified and sealed by an engineer registered in Texas.
(c) 
Areas involving new construction.
(1) 
A person may not build new construction within 200 feet of a natural gas transmission pipeline unless the fire chief determines that:
a. 
The new construction has a performance-based design that provides a minimum one-hour time period for occupant evacuation to a safe place in the event of a pipeline leak or a fire associated with the pipeline, in accordance with Chapter 25-12, Article 7 (Uniform Fire Code) or the 2000 edition of the National Fire Protection Association 101 Life Safety Code;
b. 
The new construction incorporates a system for the early detection and notification of a pipeline leak, if the fire chief determines that an appropriate system is commercially available; and
c. 
The performance-based design for occupant evacuation and the early detection and notification system are certified and sealed by an engineer registered in Texas.
(2) 
A person may not build new construction within 200 feet of a hazardous pipeline unless it complies with the standards for construction near a pipeline defined as a hazardous pipeline by the City of Austin, as prescribed by the Fire Protection Criteria Manual adopted by City of Austin.
(d) 
Areas involving a restricted pipeline area.
(1) 
Subject to subsection (b) below, a person may not place a habitable building or excavate within a restricted pipeline area.
(2) 
This prohibition does not apply to:
a. 
The pipeline or an appurtenance;
b. 
A facility that produces, consumes, processes, or stores the product transported by the pipeline, including a power generation facility;
c. 
A public or private utility line (which may include but not be limited to water and wastewater lines, stormwater and/or drainage lines) that crosses the restricted pipeline area, including an appurtenance to the line;
d. 
A utility service connection;
e. 
A road;
f. 
A surface parking lot; or
g. 
An uninhabitable structure or excavation that the city and pipeline operator determines does not disturb the pipeline or impede its operation.
(3) 
Before a person may place a road, surface parking lot, or utility line in a restricted pipeline area, the person must deliver to the city and pipeline operator a certification by a registered engineer stating that the proposed construction activity and structure are designed to prevent disturbing the pipeline or impeding its operation.
(Ordinance 1041, § 1(Exh. A), adopted 7/2/2019; Ordinance 1055, § 2(Exh. A), adopted 9/9/2019; Ordinance 1091, § 2(Exh. A), 4/21/2020; Ordinance 1136, § 2(Exh. A), adopted 2/23/2021)
(a) 
"Development permit", for purposes of this consultation zone requirement, means any permit required by the city for activity that involves construction, grade modification, excavation, blasting, land clearing, or the deposit of earth, rocks or other materials that places an additional load upon the soil. Construction that involves work totally within an existing building footprint, such as residential remodeling projects, is specifically exempted from these consultation zone requirements.
(b) 
Consultation zone distance.
The consultation zone requirement applies to development permits involving any parcel that is within 660 feet of the centerline of a natural gas transmission pipeline. The 660-foot consultation zone distance may be lessened for certain development permit activities if notice of the development permit activities and the distance changes are provided to the pipeline operator(s) by the development permit applicant and no objection is provided by such pipeline operator. There must be written documentation demonstrating that such notice has been provided to the pipeline operator(s) and that within 15 days of delivery of such for such proposed development permit activities.. The intent of this section is to provide flexibility and to avoid unnecessary paperwork and delays in the permitting process while also making sure that all activities that may impact the integrity of a natural gas transmission pipeline are given an opportunity to be thoroughly reviewed by the pipeline operator(s). The 15-day time period may be extended so long as the pipeline operator(s) has contacted the applicant and requested such extension of time.
(c) 
Consultation zone notification.
Whenever any applicant applies for a development permit within the consultation zone established for natural gas transmission pipelines, the staff at the permit counter shall notify the applicant that they are within the consultation zone, explain the relevant application procedures, and provide contact information for the applicable pipeline operator(s). This same procedure shall be followed whenever an individual inquires about development regulations or zoning restrictions for property within the consultation zone.
(d) 
Complete application for development permit within consultation zone.
A complete application for any development permit within the designated consultation zone must include written verification from the applicant that:
(1) 
The applicant has delivered notice to the pipeline operator(s) and has provided the pipeline operator(s) with documentation detailing the proposed development permit activity and where the activity is to take place; and
(2) 
That the pipeline operator(s) has either (i) responded with no objections, (ii) has failed to respond to the applicant within the 15-day time period set out above, or (iii) has provided objections to the applicant.
(3) 
The notice and written documentation shall be provided to the pipeline operator via both regular mail and certified, return receipt requested, and demonstrates that the pipeline operator(s) has received the documentation showing the proposed development permit activity and its location.
(4) 
If the pipeline operator(s) has responded, such documentation shall also be included.
(e) 
Checklist.
A checklist, provided by the city and submitted by an applicant for a development permit involving any parcel that is within 660 feet of the centerline of a natural gas transmission pipeline must reference the natural gas transmission pipeline(s) and provide information concerning any impact the activity will have upon the integrity of the natural gas transmission pipeline(s).
(Ordinance 1041, § 1(Exh. A), adopted 7/2/2019; Ordinance 1055, § 2(Exh. A), adopted 9/9/2019; Ordinance 1091, § 2(Exh. A), 4/21/2020; Ordinance 1136, § 2(Exh. A), adopted 2/23/2021)
(a) 
Prior to the construction and/or operation of natural gas through a transmission pipeline or hazardous materials through a hazardous pipeline as both are defined in [section] 8-251 on or after the date of passage of [the ordinance from which this section derives], the pipeline operator shall provide to the city certification that the design and installation of the natural gas transmission pipeline(s) or hazardous pipeline(s) meet all state and federal requirements. This certification is required for informational purposes only; the City does not assert authority to enforce these state and federal requirements.
(b) 
Transmission pipelines, hazardous pipelines, gathering lines and production lines within the city limits or extraterritorial jurisdiction where they are within, under, or touch city rights-of-way, roads, easements or any other city property shall be constructed in accordance with the city's ordinances.
(c) 
The city may also require that a natural gas transmission pipeline be redesigned or relocated should it conflict with the alignment and depth of a gravity dependent proposed utility infrastructure.
(d) 
Review by the city for all proposed natural gas transmission pipelines through private residential areas shall be required prior to the issuance of a pipeline permit for the commencement of pipeline construction.
(e) 
All known oil and gas pipelines, including hazardous pipelines and all private or public easements must be indicated on a plat.
(f) 
Only one pipeline shall be considered and authorized in any right-of-way, road, easement or any other city property under each permit application.
(g) 
A pipeline permit application shall be required as follows:
(1) 
Applications for natural gas transmission pipeline, hazardous pipelines, or other activities regulated by section 8-251 shall be submitted to the city in a form prescribed by the city.
(2) 
Plans submitted with each application for a pipeline permit shall be in a format approved by the city showing the dimensions and locations of the pipeline and related items or facilities, as well as all proposed lift stations, pumps or other service structures related to such pipeline and the location, type and size of all existing utilities, drainage, rights-of-way and roadway improvements. The plans must additionally show the elevation and location of all known public utilities within 15 feet of the centerline of the proposed pipeline. Any application that fails to meet these requirements will be returned as incomplete to the applicant.
(3) 
The following information shall be provided in the application:
a. 
The name, business addresses and telephone numbers of the pipeline operator;
b. 
The names, titles and telephone numbers of the following:
1. 
The person signing the application on behalf of the pipeline operator; and
2. 
The person designated as the principal contact for the submittal.
c. 
The origin point and the destination of the proposed subject pipeline;
d. 
A text description of the general location of the proposed subject pipeline;
e. 
Identification of the substance to be transported through the proposed subject pipeline;
f. 
A copy of the substance material safety data sheet (MSDS);
g. 
Engineering plans, drawings and/or maps with summarized specifications showing the horizontal location, covering depths and location of shutoff valves of the proposed subject pipeline. To the extent that information can be obtained, drawings shall show the location of other pipelines and utilities that will be crossed or paralleled within 15 feet of the proposed subject pipeline right-of-way;
h. 
Detailed cross section drawings for all public street rights-of-way and public utility easement crossings;
i. 
The proposed method or methods to be used for the installation of the pipeline;
j. 
Methods to be used to prevent both internal and external corrosion;
k. 
A binder of certificates of all bonds and insurance; and
l. 
A proposed alignment strip map showing name and address of all affected property owners.
(h) 
Fees associated with such pipeline permit(s) are as follows:
(1) 
Pipeline permit application fee.
Every application for a pipeline permit shall be accompanied by a permit fee of $2,500.00.
(2) 
Pipeline right-of-way review.
Each pipeline permit application for use of a public right-of-way or public utility easement is subject to review and determination by the city's engineer or his/her designee.
a. 
Permittees using the public right-of-way or a public utility easement shall enter into a city-approved use agreement with the city prior to receiving a pipeline permit authorizing the use of the city right-of-way or public utility easement.
b. 
In the event a pipeline permit application for use of public right-of-way or a public utility easement is denied, an applicant may appeal such denial within five days of receipt of written notice of such denial to the city manager. The decision of the city manager may be appealed to the city council within five days of receipt if the city manager's decision. The city council's decision shall be final.
(3) 
Pipeline right-of-way annual use fee.
Annual fee of $3.00 times the number of rods of public ROW or public utility easements occupied. Payment for the first year is due within 30 days of approval and payment for subsequent years is due prior to each anniversary of the effective date of the agreement. This fee may, in the sole discretion of the city, be adjusted for inflation as long as the fee does not exceed the cost to the city of administering, supervising, inspecting, and otherwise regulating the location of pipelines occupying public rights-of-way and public utility easements.
(i) 
Insurance and bonds.
(1) 
Each pipeline operator of a natural gas transmission pipeline or a hazardous pipeline during the term of its regulated pipeline permit must carry public liability insurance with a carrier rated "A" or better by A.M. Best in a minimum amount of $1,000,000.00 for one person and $5,000,000.00 for one accident and property damage insurance in the amount of $10,000,000.00 for one accident.
(2) 
Each pipeline operator shall provide and maintain in full force and effect during the term of its regulated pipeline permit insurance with the following minimum limits:
a. 
Worker's compensation at statutory limits.
b. 
Employer's liability insurance with the following minimum limits for bodily injury by:
1. 
Accident, $1,000,000 per each accident; and
2. 
Disease, $1,000,000 per employee with a per-policy aggregate of $1,000,000.
3. 
Commercial general liability coverage, including blanket contractual liability, products and completed operations, personal injury, bodily injury, broad form property damage, operations hazard, pollution, explosion, collapse and underground hazards for $2,000,000 per occurrence and aggregate policy limit of $2,000,000.
4. 
Automobile liability insurance (for automobiles used by the pipeline operator in the course of its performance under the pipeline permit, including employer's nonownership and hired auto coverage) for $2,000,000 combined single limit per occurrence.
5. 
Umbrella liability insurance following the form of the primary liability coverage described in subsections (a) and (b) and providing coverage with minimum combined bodily injury (including death) and property damage limit of $25,000,000 per occurrence and $25,000,000 annual aggregate. Increased primary liability limits equivalent to the umbrella liability insurance limits specified will satisfy the umbrella liability insurance requirements.
c. 
Performance bond or irrevocable letter of credit.
1. 
Before issuance of a pipeline permit, the pipeline operator shall submit to the city a performance bond or irrevocable letter of credit approved as to form by the city attorney in the amount of $100,000.00.
2. 
The performance bond is effective upon the issuance of the pipeline permit and must remain in full force and effect until all work under the terms of the pipeline permit has been completed.
3. 
The performance bond may be amended to include other permitted pipeline permits.
(Ordinance 1041, § 1(Exh. A), adopted 7/2/2019; Ordinance 1055, § 2(Exh. A), adopted 9/9/2019; Ordinance 1091, § 2(Exh. A), 4/21/2020; Ordinance 1136, § 2(Exh. A), adopted 2/23/2021)
(a) 
The pipeline operator of a natural gas transmission pipeline as defined in section 8-251 shall submit a noise management plan detailing how the pipeline or any equipment or facilities including compressor stations used in the installation of the pipeline and/or, transportation of natural gas complies with the maximum permissible noise levels of this section. The noise management plan must:
(1) 
Identify operation noise impacts;
(2) 
Provide documentation establishing the ambient noise level prior to construction of any pipeline; and
(3) 
a. 
Detail how the impacts will be mitigated. In determining noise mitigation, specific site characteristics shall be considered, including, but not limited to, the following:
1. 
Nature and proximity of adjacent development, location and type;
2. 
Seasonal and prevailing weather patterns, including wind directions;
3. 
Vegetative cover on or adjacent to the site; and
4. 
Topography.
b. 
The pipeline operator shall be responsible for verifying compliance with this section and the noise management plan after the installation of the noise generation equipment.
(b) 
No natural gas transmission pipeline or any equipment or facilities including compressor stations associated with such pipeline shall be operated at any location within the city in such a manner so as to create any noise, that exceeds 55dB(A) at the closest noise sensitive areas (i.e., homes, businesses, parks, churches, etc.).
(c) 
The sound level meter used in conducting noise evaluations shall meet the American National Standard Institute's Standard for sound meters or an instrument and the associated recording and analyzing equipment which will provide equivalent data.
(d) 
A citation may be immediately issued for failure to comply with the provisions of this section. However, if the pipeline operator is in compliance with the approved noise management plan, and a violation still occurs, the pipeline operator will be given 24 hours from notice of noncompliance to correct the violation from an identified source before a citation is issued. Additional extensions of the 24-hour period may be granted in the event that the source of the violation cannot be identified after reasonable diligence by the operator.
(Ordinance 1041, § 1(Exh. A), adopted 7/2/2019; Ordinance 1055, § 2(Exh. A), adopted 9/9/2019; Ordinance 1091, § 2(Exh. A), 4/21/2020; Ordinance 1136, § 2(Exh. A), adopted 2/23/2021)
Upon discovery of a pipeline emergency or incident, any affected pipeline operator shall as soon as practical communicate to the city's 911 system the following information:
(1) 
A general description of the emergency or incident;
(2) 
The location of the emergency or incident;
(3) 
The name and telephone number of the person reporting the emergency or incident;
(4) 
The name of the pipeline operator;
(5) 
Whether or not any hazardous material is involved and identification of the hazardous material so involved; and
(6) 
Any other information as requested by the emergency dispatcher or other such official at the time of reporting the emergency or incident.
(Ordinance 1041, § 1(Exh. A), adopted 7/2/2019; Ordinance 1055, § 2(Exh. A), adopted 9/9/2019; Ordinance 1091, § 2(Exh. A), 4/21/2020; Ordinance 1136, § 2(Exh. A), adopted 2/23/2021)
(a) 
If non-emergency repairs necessitate excavation of a natural gas transmission pipeline or hazardous pipeline in the public rights-of-way, utility easements, or city owned property, the pipeline operator shall send notification to occupants of business establishments and residential dwellings located adjacent to the pipeline to be excavated at least five days prior to commencing such repairs.
(b) 
If above-ground non-emergency repairs that are not routine maintenance are required and involve the public rights-of-way, utility easements or city owned property, the pipeline operator shall send notification to occupants of businesses and residential dwellings located within 200 feet from the centerline of the pipeline section to be repaired at least five days prior to commencing such repairs.
(c) 
The notice required herein shall be sent by United States regular mail, postage prepaid mailed at least five business days prior to commencing any non-emergency repair; provided, however, that the pipeline operator may use hand delivery notice as an alternative, at the pipeline operator's discretion.
(Ordinance 1041, § 1(Exh. A), adopted 7/2/2019; Ordinance 1055, § 2(Exh. A), adopted 9/9/2019; Ordinance 1091, § 2(Exh. A), 4/21/2020; Ordinance 1136, § 2(Exh. A), adopted 2/23/2021)
Nothing in this subsection grants permission for the use of any public street, public rights-of-way, utility easements or city-owned property. In the event a pipeline operator wishes to undertake any natural gas transmission pipeline construction on, over, under, along or across any public rights-of-way, utility easements or other city-owned property, the pipeline operator shall apply for and execute a written agreement with the city governing the terms and conditions for such use; obtain all required permits and comply with any other applicable provisions of the city code.
(Ordinance 1041, § 1(Exh. A), adopted 7/2/2019; Ordinance 1055, § 2(Exh. A), adopted 9/9/2019; Ordinance 1091, § 2(Exh. A), 4/21/2020; Ordinance 1136, § 2(Exh. A), adopted 2/23/2021)
Nothing in these provisions shall be construed as an assumption by the city of any responsibility of a pipeline operator of a pipeline not owned by the city.
(Ordinance 1041, § 1(Exh. A), adopted 7/2/2019; Ordinance 1055, § 2(Exh. A), adopted 9/9/2019; Ordinance 1091, § 2(Exh. A), 4/21/2020; Ordinance 1136, § 2(Exh. A), adopted 2/23/2021)
In keeping with the Natural Gas Pipeline Safety Act of 1968 and 49 CFR § 192.614, "Damage Prevention Program," 49 CFR § 192.615, "Emergency Plans," the Hazardous Liquids Safety Act of 1979, and 49 CFR § 195.408, "Communications," 49 CFR § 195.440, "Public Awareness," and the Community Right-to-Know Act, 40 CFR Parts 350-374, all as amended:
(1) 
Annually, all pipeline operators will provide affected landowners, public officials and emergency providers with appropriate public awareness information as outlined in API 1162.
(2) 
Each pipeline owner or operator shall maintain a public education program that is communicated to residents and business establishments within 1,000 feet of the centerline of a pipeline.
(3) 
Public education information shall be communicated at least annually in both English and Spanish.
(Ordinance 1041, § 1(Exh. A), adopted 7/2/2019; Ordinance 1055, § 2(Exh. A), adopted 9/9/2019; Ordinance 1091, § 2(Exh. A), 4/21/2020; Ordinance 1136, § 2(Exh. A), adopted 2/23/2021)
(a) 
A person is criminally responsible for a violation of this article if the person:
(1) 
Fails to obtain a city permit as required in [section] 8-253 herein;
(2) 
Fails to comply with the city's ordinances; or
(3) 
Fails to comply with any provision of this article.
(b) 
A person who knowingly violates any provision of this article is guilty of a separate offense for each day or portion of a day during which the violation is continued. Each offense is punishable by a fine of $2,000. This fine shall be doubled for the second conviction of the same offense within any 24-month period and trebled for the third and any subsequent convictions of the same offense within any 24-month period.
(c) 
To the extent that this chapter 8, building regulations, refers to or incorporates any requirements of federal or state law, the violation of any such requirements of federal or state law shall not be subject to the provisions of this section 8-260.
(Ordinance 1041, § 1(Exh. A), adopted 7/2/2019; Ordinance 1055, § 2(Exh. A), adopted 9/9/2019[1]; Ordinance 1091, § 2(Exh. A), 4/21/2020; Ordinance 1136, § 2(Exh. A), adopted 2/23/2021)
[1]
Editor's note—This ordinance also repealed former § 8-260, insurance and bonds, and renumbered the remainder of the article.
(a) 
In the event a natural gas transmission pipeline is placed within any public right-of-way under the jurisdiction of the city, the owner/operator shall comply with the right-of-way use regulations as provided in this city's Code of Ordinance and obtain an appropriate franchise, permit or authorization for the use of such right-of-way.
(b) 
To the extent that the provisions of this article conflict with the city's right-of-way use ordinance, this article shall apply.
(c) 
All right-of-way use agreements that have been entered into and approved since September 10, 2019, are currently limited to a single pipeline in such right-of-way and such limitation shall not be removed or revised without city council approval.
(Ordinance 1041, § 1(Exh. A), adopted 7/2/2019; Ordinance 1055, § 2(Exh. A), adopted 9/9/2019; Ordinance 1091, § 2(Exh. A), 4/21/2020; Ordinance 1136, § 2(Exh. A), adopted 2/23/2021)
(a) 
This section applies to a use that is nonconforming because of its proximity to a natural gas transmission pipeline or hazardous pipeline under sections 8-251 or 8-252.
(b) 
Proximity to a natural gas transmission pipeline or hazardous pipeline does not solely cause a structure or area to be noncomplying under article VII, nonconforming uses and structures.
(c) 
If there is a conflict between the regulations prescribed by this section and the regulations as determined by article VII, nonconforming uses and structures, this provision controls.
(Ordinance 1041, § 1(Exh. A), adopted 7/2/2019; Ordinance 1055, § 2(Exh. A), adopted 9/9/2019; Ordinance 1091, § 2(Exh. A), 4/21/2020; Ordinance 1136, § 2(Exh. A), adopted 2/23/2021)