A.
All regulated activities shall be conducted, operated, and maintained in accordance with the requirements set forth in Articles III, VII, and VIII of this chapter. When a SWM site plan is required by this chapter, all regulated activities shall be performed in accordance with the requirements of the final approved SWM site plan.
B.
The Municipal Engineer or other municipal designee shall be provided access to the site to inspect all phases of the erosion and sediment control measures and installation of the permanent BMPs and conveyances at such times as deemed appropriate by the Municipal Engineer or other municipal designee.
C.
Periodic inspections may be made by the Municipal Engineer or other designee during construction. A set of design plans approved by the Municipality shall be on file and available for viewing at the site throughout the duration of the construction activity.
D.
Inspections, including but not limited to a final inspection, of all constructed BMPs, conveyances, or other stormwater facilities, and related improvements may be conducted by the Municipal Engineer or other designee to confirm compliance with this chapter and with the final approved SWM site plan prior to the issuance of any occupancy permit, use permit, or other form of final approval of the project by the Municipality.
E.
If an NPDES permit for stormwater discharges associated with construction activities was required for the regulated activity, a notice of termination (NOT) approval must be obtained upon completion of construction prior to final approval of the project by the Municipality.
F.
Upon completion of construction, every permanent stormwater BMP, conveyance, or other stormwater management facility constructed or used as part of the regulated activity shall be operated, maintained, and inspected by the landowner, or other designated person, in accordance with the O&M plan and O&M agreement approved by the Municipality.
G.
The Municipality or its designee may periodically inspect any permanent stormwater BMP, conveyance or stormwater management facility for compliance with this chapter, an approved O&M plan, or an approved O&M agreement, per the provisions of Article IX. The Municipality may inspect at any time it has reason to believe a violation exists. The Municipality may pursue enforcement for violations consistent with the provisions of Article IX.