A.
Within six months after Township Planning Commission approval of the preliminary subdivision or land development plat, a final subdivision or land development plat and all necessary supplementary data shall be delivered to the Township. However, an extension of time may be granted by the Township Planning Commission upon written request. In any case, § 385-9 of this chapter shall govern the application of new regulations enacted in the interim, as well as scheduling requirements.
B.
The final plat shall conform in all respects to the preliminary plat as previously approved by the Township Planning Commission and shall incorporate all modifications or conditions required at the time of approval of the preliminary plat.
C.
The Township Planning Commission may permit submission of the final plat in sections or phases, each covering a reasonable portion of the entire proposed subdivision of land development as shown on the approved preliminary plat. In any case, § 385-9 of this chapter shall govern the phasing of development for five years or more.
D.
Submission of final plats with preliminary plats is not recommended. However, a subdivider or developer may do so at their own risk. The preliminary plat shall be considered first, but at the discretion of the Planning Commission both preliminary and final plats can be approved at the same meeting.
E.
If the necessity for a preliminary plat is waived, at the discretion of the Planning Commission, the subdivider or developer shall comply with § 385-27B and § 385-27D(3), in addition to the other requirements of this section.