A.
All construction of sewage systems shall be under the jurisdiction of the Township, either directly, or through inspectors under the supervision of the Township Engineer.
(1)
The Township Engineer and the applicant's engineer shall enforce compliance with the approved plans and specifications.
(2)
The Township Engineer shall have the authority to have work discontinued in the event of non-compliance.
(3)
The applicant shall furnish the name of the occupant, the street address, and lot and block number to the Township at least two weeks prior to a request for the certificate of occupancy from the Construction Code Official to assure that the lateral inspection has been accomplished, and all fees have been paid.
(4)
No sewer connections shall be made to the appropriate street main whether tested or not unless under the supervision and inspection of the representative for the Township. Clean-out installations are subject to review and approval by the licensed operator prior to the issuance of a certificate of occupancy.
B.
A temporary, leak proof bulkhead type plug shall be installed in the upstream (inlet) side of the manhole furthest downstream in any sewer main or branch under construction and shall remain intact and unloosened until permission is received from the Township to remove same. This permission will not be granted until each section of the sewer has been cleaned and flushed in a manner acceptable to the Township.