[Ord. No. 3-2023, 7/18/2023]
1. 
All SWM site plan materials shall be submitted to the Township in a format that is clear, concise, legible, neat, and well organized; otherwise, the SWM site plan shall not be accepted for review and shall be returned to the applicant. The following items shall be included in the SWM site plan:
A. 
Written Description. A written description of the following information shall be submitted:
(1) 
General description of the project and the overall stormwater management concept for the project designed in accordance with § 23-302.
(2) 
General description of permanent stormwater management techniques, including construction specifications of the materials to be used for stormwater management facilities.
(3) 
Complete hydrologic, hydraulic, and structural computations for all stormwater management facilities and assumptions and criteria used in the design of the stormwater management facilities.
(4) 
A determination of site conditions in accordance with the BMP Manual. A detailed site evaluation shall be completed for projects proposed in areas of carbonate geology or karst topography, and other environmentally sensitive areas, such as brownfields.
(5) 
Stormwater runoff design computations and documentation as specified in this chapter, or as otherwise necessary to demonstrate that the maximum practicable measures have been taken to meet the requirements of this chapter, including the recommendations and general requirements in § 23-301 of this chapter.
(6) 
The effect of the project (in terms of runoff volumes and peak flows) on adjacent properties and on any existing municipal stormwater collection system that may receive runoff from the development site.
(7) 
Expected project time schedule.
(8) 
Development stages (project phases) if so proposed.
(9) 
An operation and maintenance (O&M) plan for all existing and proposed physical stormwater management facilities. This plan shall address long-term ownership and responsibilities for O&M as well as schedules and costs for O&M actives.
(10) 
A justification must be included if BMPs other than green infrastructure methods and LID practices are proposed to achieve the volume, rate, and water quality controls under this chapter.
(11) 
Provisions for permanent access and/or maintenance easements for all physical SWM BMPs, such as ponds and infiltration structures, as necessary to implement the operation and maintenance (O&M) plan.
B. 
Maps. Map(s) of the project area shall be submitted on 24-inch x 36-inch sheets and/or shall be prepared in a form that meets the requirements for recording at the offices of the Recorder of Deeds of Monroe County. The contents of the map(s) shall include, but not be limited to:
(1) 
A location map at a scale of 1" = 2,000' or less showing the location of the project relative to highways, municipalities, or other identifiable landmarks.
(2) 
The name of the development, the name and address of the applicant, the address of the property, and the name and address of the individual or firm preparing the SWM site plan.
(3) 
The date of submission.
(4) 
A graphic and written scale of one inch equals no more than 50 feet; for tracts of 20 acres or more, the scale shall be one inch equals no more than 100 feet.
(5) 
A North arrow, with a notation of whether it is true or magnetic.
(6) 
The boundaries of the total property and, if different, development site boundary and size with distances marked to the nearest foot and bearings to the nearest degree.
(7) 
Names, numbers and rights-of-way widths of adjoining roads.
(8) 
Locations of existing streams, lakes, ponds, wetlands or other waters of this commonwealth within the development site.
(9) 
Locations of wooded areas and tree masses, buildings and structures, rock outcrops, paved areas, sidewalks, culverts, storm sewers, swales, utilities, and all other significant man-made features.
(10) 
The locations of existing and proposed on-lot wastewater facilities and water supply wells.
(11) 
Floodplain and floodway boundaries, riparian buffers, existing drainage courses, areas of natural vegetation to be preserved, the total extent of the upstream area draining through the site, and pre- and post-development drainage areas.
(12) 
Existing and proposed contours at intervals of two feet. In areas of steep slopes (greater than 15%), five-foot contour intervals may be used.
(13) 
The locations of all existing and proposed utilities, sanitary sewers, and water lines within 50 feet of property lines.
(14) 
The location(s) of any wellhead protection zones.
(15) 
Soil names, boundaries, hydrologic group, and limitations.
(16) 
Limits of earth disturbance, including the type and amount of impervious area that would be added.
(17) 
Proposed structures, roads, paved areas, impervious surfaces, buildings and other land cover.
(18) 
Existing and proposed land use(s).
(19) 
A key map showing all existing man-made features beyond the development site boundary that would be affected by the project.
(20) 
Location of all open channels.
(21) 
Overland drainage patterns and swales.
(22) 
The location of all erosion and sediment control facilities.
(23) 
The location of permanent access and/or maintenance easements for all physical SWM BMPs.
(24) 
Plans, profiles, and details of all SWM BMPs, including, but not limited to, drainage structures, pipes, open channels, and swales.
(25) 
A note on the plan indicating the location and responsibility for maintenance of stormwater management facilities that would be located off-site.
(26) 
A statement, signed by the applicant, acknowledging that any revision to the approved SWM site plan must be approved by the Township and that any revised erosion and sediment control plan must be submitted to the Conservation District for a determination of adequacy.
(27) 
The following signature block for the qualified professional:
"I, [qualified professional], on this date, [date of signature], hereby certify that the SWM site plan meets all design standards and criteria of the [name of applicable Act 167 Plan] and Stroud Township Stormwater Management Ordinance."
(28) 
Isolation distances from wells, buildings, and septic systems, as noted in the Pennsylvania Stormwater Best Management Practices (BMP) Manual.
C. 
Supplemental Information.
(1) 
A soil erosion and sediment control plan, where applicable, and letter of adequacy from the Conservation District.
(2) 
A declaration of adequacy and highway occupancy permit from the PennDOT District Office when utilization of a PennDOT storm drainage system is proposed.
(3) 
Wetland delineation report and/or a jurisdictional determination from the U.S. Army Corps of Engineers.
(4) 
For any activities that require an NPDES permit for stormwater discharges from construction activities, or a DEP joint permit application, a PennDOT highway occupancy permit, or any other permit under applicable state or federal regulations, or are regulated under 25 Pa. Code Chapter 105 or Chapter 106, the proof of application for said permit(s) or approvals shall be submitted.
[Ord. No. 3-2023, 7/18/2023]
1. 
The applicant shall submit a complete drainage plan application, with all required plans and supplemental materials, as specified in this chapter. No application is complete without the required fee. The application shall be coordinated with the state and federal permit process and the SALDO review process.
A. 
For those regulated activities which require SALDO approval, the SWM site plan shall be submitted by the applicant as part of the preliminary plan submission.
B. 
Three copies of the SWM site plan shall be submitted along with the required application fee.
C. 
Any submissions found incomplete shall not be accepted for review and shall be returned to the applicant with a notification in writing of the specific manner in which the submission is incomplete.
D. 
Complete applications shall be distributed as follows:
(1) 
Two copies to the Township.
(2) 
Two copies to the Conservation District.
(3) 
One copy to the Township Engineer.
(4) 
One copy to the Monroe County Planning Commission.
[Ord. No. 3-2023, 7/18/2023]
1. 
The Township shall review the SWM site plan for consistency with the provisions of this chapter.
2. 
The Township shall notify the applicant in writing within 45 days whether the SWM site plan is approved, approved with conditions or disapproved. If the SWM site plan involves a subdivision and land development plan, the notification shall occur within the time period allowed by the Municipalities Planning Code[1] (90 days) unless the time requirement is waived in writing by the applicant. If a longer notification period is provided by other statute, regulation, or ordinance, the applicant will be so notified by the Township.
[1]
Editor’s Note: See 53 P.S. § 10101 et seq.
3. 
The Township shall not unconditionally approve a SWM site plan until the applicant presents evidence that the Conservation District has found the erosion and sediment control plan adequate to meet the requirements of 25 Pa. Code Chapter 102.
4. 
If the Township disapproves the SWM site plan, the Township shall state the reasons for the disapproval in the written notice. If the Township approves the SWM site plan with conditions, the Township shall state the conditions in the written notice.
[Ord. No. 3-2023, 7/18/2023]
Any modification to an approved SWM site plan that involves a change in stormwater management BMPs or techniques, or that involves the relocation or re-design of stormwater management BMPs, or that is necessary because soil or other conditions are not as stated on the SWM site plan, as determined by the Township, shall require a resubmission of the modified SWM site plan in accordance with this Part.
[Ord. No. 3-2023, 7/18/2023]
A disapproved SWM site plan may be resubmitted, with the revisions addressing the Township's concerns, to the Township in accordance with this Part. All applicable fees shall accompany a resubmission of a disapproved SWM site plan.
[Ord. No. 3-2023, 7/18/2023]
The Township's approval of an SWM site plan authorizes the regulated activities contained in the SWM site plan for a maximum term of validity of five years following the date of approval. The Township may specify a term of validity shorter that five years in the approval for any specific SWM site plan. If work shown on an approved SWM site plan is not completed according to § 23-407 within the term of validity, then the Township may consider the SWM site plan disapproved and may revoke any and all permits.
[Ord. No. 3-2023, 7/18/2023]
1. 
The developer shall be responsible for providing as-built plans of all SWM BMPs included in the approved SWM site plan. The as-built plans and an explanation of any discrepancies with the construction plans shall be submitted to the Township.
2. 
The as-built plan shall include a certification signed by a qualified professional verifying that all permanent stormwater BMPs have been constructed according to the approved plans and specifications. The latitude and longitude coordinates for all permanent stormwater BMPs must also be submitted, at the central location of the BMPs. If any licensed qualified professionals contributed to the construction plans, then a licensed qualified professional must sign the completion certificate.
3. 
After receipt of the completion certification by the Township, the Township may conduct a final inspection.