If a public notice of application is required, the director shall issue a notice of development application, within 14 days of issuing a determination of completeness under BLMC § 14.40.030, containing the following information:
A.
Name of the applicant(s).
B.
Date of application.
C.
Date of issue for the determination of completeness.
D.
Location of the project.
E.
Project description (summary).
F.
Requested and necessary approvals, actions, and/or studies (summary).
G.
Duration of the public comment period.
H.
Identification of existing applicable environmental documents, if any.
I.
A determination of specific critical areas that are or are not affected by the proposed development.
J.
City staff contact information.
K.
Date, time, and place of the public hearing for the permit if a public hearing is required and the date of the hearing has been set at the time of the notice of application.
L.
A statement that, barring excluded periods, the decision on the application is anticipated within 120 days of the determination of completeness.
M.
Other information as the director deems necessary.