Time estimates contained in this section (expressed in calendar days) shall apply when the city processes licenses for all private projects and those governmental proposals submitted to the city by other agencies. The actual time may vary with the complexity of the project, availability of staff, cooperation of agencies with jurisdiction or expertise, etc. Time periods for making threshold determinations shall commence upon payment of fees.
A. Categorical Exemptions. The city will normally identify whether an action is categorically exempt within seven days of receiving a completed application.
B. Threshold Determinations. When the city is lead agency for a proposal, the following threshold determination timing requirements apply:
1. If a DS is made concurrent with the notice of application, the DS and scoping notice shall be combined with the notice of application (RCW
36.70B.110). Nothing in this subsection prevents the DS/scoping notice from being issued before the notice of application. If sufficient information is not available to make a threshold determination when the notice of application is issued, the DS may be issued later in the review process.
2. If the city is lead agency and project proponent or is funding a project, the city may conduct its review under SEPA and may allow appeals of procedural determinations prior to submitting a project permit application.
3. If an open record predecision hearing is required, the threshold determination shall be issued at least fifteen days before the open record predecision hearing (RCW
36.70B.110(6)(b)).
4. The optional DNS process in WAC
197-11-355 may be used to indicate on the notice of application that the lead agency is likely to issue a DNS. If this optional process is used, a separate comment period on the DNS may not be required (refer to WAC
197-11-355(4)).
(Ord. 2304 § 1 (part), 2013)