[Amended 8-1-2005 by Res. No. 08012005; 9-15-2008]
Rates to be charged for service furnished by the system shall be as follows:
A.
Sewer use charges. All sewer use charges shall be made against each user and premises based upon rates to be determined by resolution.
B.
Connection charge.
(1)
Connection charge. Connection charges that are determined under this section shall henceforth be determined by resolution of the Township Board.
(2)
Direct and indirect connections. For each direct connection to the lines of the system there shall be charged a connection fee of the full amount set by resolution per single-family residence equivalent. For each indirect connection the charge shall be one-half of the resolution amount per single-family residence equivalent or user charge unit.
(3)
Indirect connection. An indirect connection shall be defined as one made to lines added to the system after its original construction, the cost of which is paid from special assessments or private funds, to include public funds expended without special assessing to the property.
(4)
Equivalent user factor; user charge units. Properties containing only a single-family residence equivalent shall pay connection charges as above defined multiplied by one unit for each single-family residential unit. All other uses shall pay the above connection charges multiplied by a factor representing the ratio of sewage use by such class of premises to normal single-family residential use as determined by the Township Board and adopted by resolution. The equivalent user factor or user charge units shall be calculated for any premises based on the use of the property at the time of the original application for sewer service of connection for sewer service. Whenever the use of the property is changed, modified or enlarged therefrom, an additional connection charge based on the amount of units resulting from the change shall be further paid. The equivalent user factor or number of user charge units shall not be revised below that applicable to the original application for connection or in effect at the time of connection.
(5)
Payment of connection charge. Connection charges shall immediately constitute a lien on the premises served on the date of the publication of the notice of availability and shall be due and payable as follows:
(a)
Connection of new structure to existing sewer. Where a new structure is connected to an existing sewer, the amount due for the single-family residence equivalent shall be payable prior to and as a condition of the issuance of a building permit.
(b)
Connection of structure existing when a sewer is made available. In the case where a new sewer is first made available to an existing structure, where the structure is in place and able to be lawfully occupied on the date the notice of availability is published, if the connection charge is not then paid in full, the charge may be paid in installments with interest at the annual rate of 6% per annum on the unpaid balance over a period of 10 years. If paid in installments, the first installment shall be payable upon application for the connection, and all subsequent installments plus interest shall be payable annually on July 1 of each year, to be billed effective said, and payable by September 14 of any said year. All payments shall carry the interest above to the date of payment. Any payment not paid by September 14 shall be delinquent and shall be placed on the tax roll. In addition, the Township may collect same by personal action.
(c)
Other cases. In all other cases, the connection charge shall be paid in full and shall be due and constitute a lien on the date the notice of availability is published.
C.
Special rates. For miscellaneous or special services for which a special rate shall be established, such rates shall be fixed by the Township Board.
D.
Billing.
(1)
Bills for sewer use charges shall be rendered quarterly on January 1, April 1, July 1, and October 1, payable without penalty within 30 days after the date thereon. Payments received after such period shall bear a penalty of 6% of the amount of the bill.
(2)
Bills for connection charge installments and interest and penalties shall be rendered on July 1 of every year. Payments received after September 14 following said billing shall bear a penalty of 6% of the amount of the bill.