The city of Milton shoreline master program, adopted by Section 2 of Ordinance No. 1803, is adopted by reference as though set forth herein in full.
(Ord. 1290 § 3, 1996; Ord. 1803 § 3, 2012)
If the sum of the proposed revision and any previously approved revisions do not meet the criteria above, an application for a new shoreline permit must be submitted. If the revision involves a conditional use or variance which was conditioned by the Department of Ecology, the revision also must be reviewed and approved by the Department of Ecology (see WAC 173-27-100). |
A city or department decision on revision to the permit may be appealed to the Shorelines Hearings Board within 21 days of such decision, in accordance with RCW 90.58.180 and WAC 173-27-100. |
Construction allowed by the revised permit that is not authorized under the original permit is undertaken at the applicant's own risk until the expiration of the appeals deadline. |