It is the responsibility of the permittee or his/her assignee to notify the city engineer at the completion of the following phases of work for inspections and for scheduling of future inspections:
A.
Preconstruction Inspection. Prior to the commencement of any other work, the inspection of sediment and erosion control devices shall take place when installation of all the sediment and erosion control devices has been completed according to approved plans. Only the minimum area necessary for installation of the sediment and erosion control devices shall be cleared and/or graded prior to this inspection.
B.
Rough Grading Inspection. When all rough grading is complete inspection of the site shall take place to determine the satisfactory functioning of all sediment and erosion control devices.
C.
Final Inspection. Upon completion of all construction, inspection of the site shall take place to determine that all temporary sediment and erosion control devices have been removed and that the site has been permanently stabilized.
(Ord. 1529 § 6.1, 1991)