A.
General. The purpose of maritime and shoreland development reviews function as a control for the Town to oversee proposed developments located in, or in close proximity to, designated resource protected areas so as to ensure the safe and healthful conditions of significant natural, wildlife, cultural and maritime resource.
B.
Applicability.
(1)
Kittery port authority. The Kittery Port Authority's ("Port Authority") jurisdiction extends to applications proposing any development from the navigable tidal waters to the highest annual tide or upland edge of a coastal wetland. The Port Authority, through its established rules and regulations, reviews and approves applications for piers, wharves, landings, floats, bridges, other water-dependent structures or uses.
(2)
Planning Board. The Planning Board's jurisdiction for review and approval extends to applications proposing any upland development from the highest annual tide of any water bodies or upland edge of a costal or freshwater wetland or any development located within the Shoreland, Resource Protection, and Commercial Fisheries/Maritime Uses Overlay Zones or all other structures not requiring Port Authority approval, except for applications as provided under § 16.9.1B(1).
C.
General review process and notification.
(1)
Process.
(a)
Prior to the submission of a shoreland development application with the Port Authority or the Planning Board, a preliminary application meeting between the Town Planner, Code Enforcement Officer, or designee, and the applicant or agent, shall occur to review the proposed project, performance standards and procedural requirements thereof.
(b)
If Port Authority or Planning Board review is not required, the Code Enforcement Officer and Town Planner shall review the application for compliance with this title.
(c)
If the Planning Board must review and approve a development plan application involving a pier, ramp, flotation system or principal marine structure, prior to the submission of the development plan application requiring Planning Board review, the Port Authority must review and approve any proposed pier, ramp and float system or principal marine structure application.
(d)
All required local approvals (excluding Town building permits), federal and state approvals and/or permits shall be received by the Code Enforcement Officer, prior to the issuance of a building permit.
(e)
Prior to the commencement of construction on any pier, dock, wharf, marina or any other proposed use that projects into a water body, the owner and/or developer shall apply for, and obtain, a building permit from the Code Enforcement Officer.
(2)
Notification.
(a)
If Port Authority or Planning Board review is not required, the Code Enforcement Officer shall send a written record of their findings to both the Planning Board and Port Authority.
(b)
The Town Planner must transmit copies of Planning Board decisions and the Code Enforcement Officer must transmit copies of Board of Appeals decisions and all documentation constituting the record of the decision for marine-related development to the Port Authority.
(c)
The Port Authority shall notify the applicant and the Code Enforcement Officer, in writing, of the granting of, or denial of, the applicant's request.