An application for a revision to an approved preliminary binding site plan may be submitted before a final binding site plan application is submitted, as follows:
A. Minor Revisions to an Approved Preliminary Binding Site Plan. The Director is authorized to make the determination on a minor revision to an approved binding site plan without a public hearing.
1. Defined. Minor revisions to an approved preliminary binding site plan are those which do not change: (a) the binding site plan boundaries (other than for survey discrepancies); (b) the conditions of preliminary binding site plan approval; (c) road alignments or connections and/or do not increase the number of lots by more than five percent or five lots, whichever is less.
2. Application. A complete application for a preliminary binding site plan revision shall consist of the following:
a. Application form and filing fee;
b. Site plan showing the proposed modification, using the same plan format as in the original approval;
c. Explanation in narrative form of the requested modification.
3. Processing. The following steps shall be followed in the processing of an application for a minor revision:
a. MTMC §
18.05.110, determination of completeness and requests for additional information;
d. Subsection (A)(4) of this section, determination of consistency with approval criteria;
4. Criteria for Approval. The Director shall approve, approve with conditions or deny a proposed minor preliminary binding site plan revision application, as long as the applicant demonstrates that all of the following criteria are satisfied:
b. The revision will not be inconsistent with, or cause the binding site plan to be inconsistent with, the findings, conclusions or decision made by the City in its approval of the preliminary binding site plan; and
c. Approval of the revision will not affect the ability of the collective lots in the property included in the preliminary binding site plan to function as one site with respect to, but not limited to, lot access, interior circulation, open space, landscaping, drainage facilities, facility maintenance and parking.
5. Time Limitation for Final Decision. The minor preliminary binding site plan revision application shall be approved, approved with conditions or denied within 120 days after a complete application is submitted, unless the applicant consents to an extension in writing of such time period; provided, that if an environmental impact statement is required as provided in RCW
43.21C.030, the 120-day period shall not include the time spent preparing and circulating the environmental impact statement by the City.
6. Deadline for Submission of Final Binding Site Plan Not Extended. Approval of a minor preliminary binding site plan revision shall not extend the deadline set forth in MTMC §
17.05.090 for submission of a final binding site plan application to the City.
B. Major Revisions to an Approved Preliminary Binding Site Plan. Major revisions to approved preliminary binding site plans are defined and processed as follows:
1. Defined. A major preliminary binding site plan revision is any application for a revision of a preliminary binding site plan that does not meet the definition of a minor preliminary binding site plan revision.
2. Application. An application for a major preliminary binding site plan revision shall include all of the elements of a complete preliminary binding site plan application.
3. Criteria for Approval, Time Limitation for Final Decision. The criteria for approval and the time limitation for a final decision of a major preliminary binding site plan revision shall be the same as those for a preliminary binding site plan application.
4. Deadline for Submission of Final Binding Site Plan Not Extended. The deadline for submission of the final binding site plan application in MTMC §
17.05.100 shall not be extended.
(Ord. 2658 § 2, 2015; Ord. 2811 § 19, 2022)