If a project is not categorically or ministerially exempt from CEQA, the applicant shall submit an environmental checklist on a form specified by the Director as part of a project application package. After a preliminary review of the checklist, the Director may require additional information of the applicant if necessary to make a determination of the environmental effects of the project.
The City shall complete the environmental checklist and prepare an initial study. Within 30 calendar days after accepting an application as complete, and based upon the findings of the initial study, the City, as lead agency, shall determine whether to prepare an EIR, a negative declaration, or reaffirm a previously prepared EIR or negative declaration. The 30 day period may be extended by 15 days, subject to the approval of the applicant and the lead agency.