A.
Applications for project permit type I actions involving structures five thousand square feet or over, type III and type IV actions shall not be accepted by the administrator unless the applicant has scheduled and attended a preapplication conference. The purpose of the preapplication conference is to acquaint the applicant with the requirements of the Prosser Municipal Code.
B.
The conference shall be held within fifteen days of the request.
C.
At the conference or within five working days of the conference, the applicant will be provided with the following:
1.
A form which lists the requirements for a completed application;
2.
A general summary of the procedures to be used to process the application;
3.
The references to the relevant code provisions or development standards which may apply to the approval of the application;
4.
The city's design guidelines.
D.
It is impossible for the conference to be an exhaustive review of all potential issues. The discussions at the conference or the form sent by the city to the applicant under subsection C of this section shall not bind or prohibit the city's future application or enforcement of all applicable law.
E.
Preapplication conferences for all other types of applications are optional, and requests for conferences will be considered on a time-available basis by the administrator.
(Ord. 1916 § 1 (part), 1997)