The Public Works Director may, upon recommendation of the City Engineer and application of the person or entity who posted the improvement completion assurance, authorize up to four (4) partial releases of the improvement completion assurance. The first partial release of the improvement completion assurance will not be granted until at least twenty-five percent (25%) of the landscaping or infrastructure improvements has been completed and approved by the City. Excluding the first and last release, the City will not make a partial release of the improvement completion assurance for an amount less than twenty percent (20%) of completed landscaping or infrastructure improvements that have been approved by the City. The final twenty-five percent (25%) of the improvement completion assurance being held for each utility improvement (i.e., storm drain, sewer, culinary water, pressurized irrigation, etc.) shall not be released until all required testing for the utility has been completed, passed and approved by the City.
(Ord. No. 23-2019 § 1, 11/19/2019)