Words and terms not defined shall have their ordinary meaning.
A. "Authorized signatory"
means an individual authorized to commit a party to a contract or to a change order.
B. "Change order"
means a valid instruction, from an authorized signatory of the city, that results in revised work to a contract. Change orders are appended to the original contract and become part of said contract.
C. "Contingency provision"
means a budgeted amount of money used to pay the cost of change orders and expressed as a percentage of the bid amount accepted by the city to complete the work contemplated in the bid.
D. "Contract"
shall be defined as set forth in RCW 39.04.010, and as amended in the future.
E. "Exceptional change order"
means a change order approved under the reasonable exception section of this chapter that, either singularly or in the aggregate, exceeds 10 percent of the original bid amount accepted by the city.
F. "Original contract"
means a contract exclusive of any subsequently appended change orders.
G. "Project manager"
means a direct employee of the city of Newcastle responsible for the management of a given public work.
H. "Public work"
shall be defined as set forth in RCW 39.04.010, and as amended in the future.
I. "Public work contract"
means a contract let to complete a public work.
J. "Revised work"
means the change, addition, or deletion of work within a public work contract.
(Ord. 2005-313 § 1)