The time estimates contained in this section apply when the city processes licenses for all private projects and those governmental proposals submitted to the city by other agencies. The actual time may vary with the complexity of the project, availability of staff, cooperation of agencies with jurisdiction or expertise, etc. The time estimates contained herein shall not be construed as mandatory, unless specifically required.
A. Categorical Exemptions. The city will normally identify whether an action is categorically exempt within seven days of receiving a completed application.
B. Threshold Determinations.
1. The city will normally complete threshold determinations that can be based solely upon review of the environmental checklist for the proposal within 15 working days of the date an applicant's completed application and checklist are submitted.
2. When the responsible official requires further information from the applicant or consults with other agencies with jurisdiction:
a. The city will normally request such further information within 15 working days of receiving a completed application and environmental checklist;
b. The city will normally wait no longer than 30 days for a consulted agency to respond;
c. The responsible official will normally complete the threshold determination within 15 working days of receiving the requested information from the applicant for the consulted agency.
3. When the city must initiate further studies, including field investigations, to obtain the information to make the threshold determination, the city will normally complete the studies within 30 working days of receiving a completed application and checklist.
4. The city will normally complete threshold determinations on actions where the applicant recommends in writing that an EIS be prepared, because of the probable significant adverse environmental impacts described in the application, within 15 working days of receiving a completed application and checklist.
5. The responsible official will normally respond to a request for early notice within 10 working days. The threshold determination will normally be made within 15 working days of receipt of the changed or clarified proposal, environmental checklist and/or permit application.
6. Notwithstanding any time period above, pursuant to RCW
43.21C.033, the responsible official shall make a threshold decision within 90 days after the application and supporting documentation are complete, unless the applicant requests an additional 30 days.
(Ord. 24 § 1 Exh. A, 1994)