A.
Notice of Application for Type II, III and IV Project Permits. Except for final subdivisions and final planned unit developments, notice of application for Type II, III and IV project permits is required in accordance with this chapter. The city shall publish, post and mail public notice of a project permit application as provided in NMC § 19.11.040.
1.
Contents. The notice of application shall include:
a.
The file number;
b.
The name of the applicant;
c.
The date of application, the date of the notice of completion for the application and the date of the notice of application;
d.
A description of the proposed project action and a list of the project permits included in the application and, if applicable, a list of any studies requested under NMC Title 14, Environment;
e.
The identification of other permits not included in the application, to the extent known by the city;
f.
A site plan, if applicable;
g.
The identification of existing environmental documents that evaluate the proposed project, and, if not otherwise stated on the document providing notice of application, the location where the application and any studies can be reviewed;
h.
A statement of the limits of the public comment period, which shall be 30 days following the date of notice of application, and statements of the right of any person to comment on the application, receive notice of and participate in any hearings, request a copy of the decision once made, and any appeal rights;
i.
The date, time, place and type of hearing, if applicable and scheduled at the date of notice of the application;
j.
A statement of the preliminary determination of consistency, if one has been made at the time of notice, and of those development regulations that will be used for project mitigation and consistency as provided in Chapter 19.13 NMC;
k.
Any other information determined appropriate by the city, such as the city's threshold determination, if complete at the time of issuance of the notice of application;
l.
Identification of the responsible city official;
m.
For a preliminary plat or short plat, the name and total area of the proposed plat, the number of proposed lots and typical lot sizes, and the proposed use.
2.
Time Frame for Issuance of Notice of Application.
a.
Within 14 days after the city has made a determination of completeness of a project permit application, the city shall issue a notice of application.
b.
If any open record predecision hearing is required for the requested project permit(s), the notice of application shall be provided at least 15 days prior to the open record hearing.
3.
Public Comment on the Notice of Application.
a.
The public comment period for a notice of application shall be 30 days after notice issuance.
b.
All public comments received on the notice of application must be received in the planning and land use services department by 5:00 p.m. on the last day of the comment period. Comments must be in writing, and may be mailed or personally delivered. Comments should be as specific as possible.
4.
SEPA Threshold Determination Issuance and Notice of Application.
a.
Except for a determination of significance, the city may not issue its threshold determination or issue a decision or recommendation on a project permit until the expiration of the public comment period on the notice of application.
b.
If the city issues a determination of significance pursuant to NMC Title 14, Environment, concurrently with the notice of application, the notice of application shall be combined with the determination of significance and scoping notice. The determination of significance and scoping notice may be issued prior to the notice of application.
B.
SEPA Exempt Projects. A notice of application shall not be required for project permits that are categorically exempt under SEPA, unless a public comment period or an open record predecision hearing is required.