Upon receipt of a master plan application under this chapter, and the payment of the prescribed fee in the county fee schedule, the county shall, within 28 days, issue a letter of completeness or shall identify the additional specific information required for a complete application. If no letter is sent, the application shall be deemed complete upon the twenty-ninth day after receipt of the application. If a letter is sent, the application shall be deemed complete upon receipt of the information identified in the letter. If the applicant does not submit the necessary information in writing to complete an application within a 90-day period, the county may reject the application and all vesting rights are lost.
(Ord. 1219 § 1 (Exh. A), 2010)