Upon completion of a project, and before a certificate of occupancy shall be granted, the applicant is responsible for certifying that the completed project is in accordance with the approved stormwater site plan. All applicants of projects addressing Minimum Requirement Nos. 1 through 9 are required to submit record drawings or "as-builts" of the full stormwater site plan. The drawings must accurately represent the project as constructed, and must depict the actual vertical and horizontal locations of stormwater infrastructure and facilities constructed as part of the project. The director may require that record drawings be stamped, signed and dated by a licensed surveyor or engineer. A final inspection will be conducted by public works against the approved plans and record drawings to ensure compliance, and is required before the release of any performance securities can occur.
(Ord. 3349 § 1, 2017)