1.
This By-law shall be enforced by the Building Commissioner. The Building Commissioner shall not issue a permit for the erection or alteration of any building or part thereof, unless the plans, specifications and intended use of such buildings are in all respects in conformity with the provisions of this By-law.
2.
No person shall use or permit the use of any building or part thereof hereafter erected, or altered in its use or construction in whole or in part, or any building when the open spaces in the lot upon which it stands have been reduced in area or shape, until the Building Commissioner has issued a certificate of occupancy and use under the Commonwealth of Massachusetts State Building Code, and until the Building Commissioner has issued a certificate to the effect that the building so erected or the part thereof so altered, the proposed use thereof, the size of the lot and its yards and setbacks, and all other applicable requirements, conform to the provisions of this By-law.
3.
In addition to the provisions of paragraphs 1 and 2 of this Section, no building permit or certificate of occupancy shall be issued by the Building Commissioner on an application or petition to the Board of Appeals until all of the conditions and safeguards imposed by the Board of Appeals in accordance with § 9.05, paragraph 2, regarding such application or petition have been complied with or compliance with conditions to be met at a future date has been arranged. Compliance with conditions and safeguards to be reviewed or approved by a Designated Authority shall be determined by the following procedure:
a.
Notice of Method of Compliance — The applicant shall complete and submit for signature a separate notice of compliance which shall include revised plans or other supporting material if applicable, to each board, commission, department head, or other administrative body or official (hereinafter the "Designated Authority") designated by the Board of Appeals to review or approve a specific aspect of the application or petition. The notice of compliance shall document compliance with the condition and/or intent to comply provided that adequate assurances for compliance such as the delivery of a bond or deposit as permitted in paragraph 4 are given. The sufficiency of the notice of compliance shall be within the discretion of the Designated Authority. If the Designated Authority fails to take action on the notice of compliance within 20 days of its receipt, compliance shall be determined by the Building Commissioner.
b.
Declaration of Compliance — The applicant shall deliver to the Building Commissioner all of the required notices of compliance. For any notice of compliance that has not been acted upon by a Designated Authority within the 20 day period, the applicant shall affix to that notice a statement to that effect. Upon a determination by the Building Commissioner that the requirements of paragraph 3, subparagraph a of this Section have been met, a declaration of compliance shall be issued by the Building Commissioner, copies of which shall be promptly forwarded to each Designated Authority.
c.
Building Permit — The Building Commissioner may issue a building permit once a declaration of compliance has been issued.
d.
Certificate of Occupancy — Prior to the issuance of a certificate of occupancy, the Building Commissioner shall send a notice of pending certificate of occupancy to each Designated Authority which shall have 14 days from the date of that notice to request that the certificate of occupancy be withheld. If such action is requested in writing or was requested in a notice of compliance, the certificate of occupancy shall not be issued until the Building Commissioner has received a notice of completion, which may incorporate provisions for a bond or deposit as permitted in paragraph 4, from the Designated Authority that requested such action.
In the event of disagreement on the procedural requirements of this Section, or in the event of unreasonable administrative delay, the matter shall be referred to the Board of Appeals for resolution. |
4.
The Building Commissioner shall not issue a certificate of occupancy until all required site improvements have been completed in accordance with the final project plans, except that the Building Commissioner may issue a certificate of occupancy if the applicant posts a bond or deposit with the Town in the amount of 1 1/2 times the total installed cost of uncompleted required at-grade site improvements at the time of issuance of the certificate of occupancy. If said improvements (such as landscaping and fences) are not completed within one year from the time of issuance of the certificate of occupancy, said bond or deposit shall be forfeited to the Town, and the Town shall utilize the bond or deposit to complete the required at-grade site improvements.
5.
Whenever application has been made to the Building Commissioner for a permit or certificate and the interpretation of this By-law with respect to the granting of such application is not clear, the Building Commissioner is authorized and directed to submit the matter to the Planning Board for the expression of its opinion before making their decision.
6.
Within 60 days after the date this paragraph becomes effective, (June 19, 1969), every owner of a building containing a dwelling unit the occupancy of which became legally nonconforming because of the Zoning By-law amendments adopted at the Town Meeting called for March 25, 1969, by reason of occupancy by unrelated persons shall file with the Building Commissioner a written statement for each affected dwelling unit on the form provided therefore to be known as a registration statement. The statement shall contain the following information for that dwelling unit and such other information as the Building Commissioner may require: street address, floor and apartment number, names of occupants and relationship to each other, if any type of tenancy, gross floor area, and number of parking spaces available for that dwelling unit. The registration statement shall be signed by the owner under the penalty of perjury. In the event that no registration statement is filed as required herein for any dwelling unit, it shall be presumed that on December 5, 1968, no nonconforming rights existed with respect to the occupancy of such dwelling unit by unrelated persons or parking requirements therefore.