The city shall provide a written notice of application to the public and departments and agencies with jurisdiction as provided in this section. Such notice shall not be required for project permits that are categorically exempt under SEPA, unless a public comment period or an open record predecision hearing is required.
A.
Timing. The notice of application shall be issued within 14 days after the city has made a determination of completion.
B.
Contents. The notice of application shall include:
1.
The date of application, the date of the determination of completeness, and the date of the notice of application;
2.
A description of the proposed project action and a list of the project permits included in the application and, if applicable, a list of any studies requested under RCW 36.70B.070 (Determination of completeness) or RCW 36.70B.090 (other information, changes, etc.);
3.
The location of the proposed project;
4.
The identification of other permits not included in the application, to the extent known by the city;
5.
The identification of existing environmental documents that evaluate the proposed project, and if not otherwise stated on the document providing the notice of application, the location where the application and any studies can be reviewed;
6.
A statement of the public comment period, which shall be not less than 14 days nor more than 30 days following the date of the notice of application;
a.
If an open record predecision hearing is required for the requested project permits, the notice of application shall be provided at least 15 days prior to the predecision hearing;
7.
Statements of the right of any person to comment on the application, receive notice of and participate in any hearings, request a copy of the decision once made, and any appeal rights;
8.
The date, time, place, and type of hearing, if applicable and if such hearing has been scheduled;
9.
A statement of the preliminary determination, if one has been made, of those development regulations that will be used for project mitigation, and of consistency as provided in RCW 36.70B.040 (DPMC § 19.04.040); and
10.
Any other information determined appropriate by the city.
C.
Methods of Notification. The city shall use reasonable methods to give the notice of application to the public and agencies with jurisdiction, including posting site-specific application sites, posting notice at the City Hall and post office, plus at other public locations deemed appropriate by the city, and publishing notice in the city's official newspaper as set forth in DPMC § 19.16.050.
D.
Withholding of Decisions. Except for a threshold determination of significance (DS), the city shall not issue a threshold determination or issue a decision or a recommendation on a project permit until the expiration of the public comment period on the notice of application.
(Ord. 722 § 175, 1998)