(1)
Concurrently with issuing a letter of completeness under MMC § 22G.010.050, or within 14 days of an application being deemed complete, the city shall issue a notice of development application. The notice shall include but not be limited to the following:
(a)
The name of the applicant;
(b)
Date of application;
(c)
The date of the letter of completeness;
(d)
The location of the project;
(e)
A project description;
(f)
The requested approvals, actions, and/or required studies;
(g)
A public comment period not less than 14 nor more than 30 days. The length of the comment period will be based on complexity of the project, as determined by the director;
(h)
Identification of existing environmental documents;
(i)
A city staff contact and phone number; and
(j)
A statement that the decision on the application will be made within the required review time frames established in MMC § 22G.010.010(3).
(2)
The notice of development application shall be posted on the subject property, posted on the city's website, published once in a newspaper of general circulation and mailed to all owners of real property located within 300 feet of any boundary of the subject property.
(3)
The notice of development application shall be issued prior to and is not a substitute for required notice of a public hearing.
(4)
A notice of application is not required for the following actions:
(Ord. 2852 § 10 (Exh. A), 2011; Ord. 3256 § 4 (Exh. D), 2023; Ord. 3328 § 3 (Exh. C), 2024)