(1)
Water and Sewer Usage Charge Rates.
(a)
Equivalent Residential Unit (ERU) Rate Method. The monthly equivalent residential unit rate or monthly base rate shall be the following:
(i) | Water | $65.00 – All Districts |
(ii) | Sewer | $65.00 |
(b)
Metered Usage Rate Method Cost per Month.
(i) | Water only | $6.00 per 1,000 over 6,000 gallons |
Abnormally strong sewage waste, when allowed, will be charged based on the formula in TTC § 13.40.070. (A lesser amount may be negotiated based on improvements provided by the applicant.)
(2)
Application Fees (Sewer and/or Water).
(a)
Application or transfer service fees are $50.00 for individual services.
(3)
Connection Charges.
(a) | Security deposit | Reserved | |
(b) | Sewer connection fee | ||
(i) | Less than 20 feet (new) | $4,750.00 | |
(ii) | Greater than 20 feet | Time and materials | |
(iii) | Inspection fee (to tie into sewer line) | $350.00 | |
(c) | Water connection fee | ||
(i) | Service line, valving, fitting (tap in) and meter | $4,750.00 (3/4 x 3/4) base fee | |
$1,200.00 (1 x 1) extra fee | |||
$1,600.00 (1-1/2 x 1-1/2) extra fee | |||
$2,000.00 (2 x 2) extra fee | |||
$3,500.00, plus time and materials (3 and over) extra fee | |||
(ii) | 1" or larger service line | Time and materials | |
(d) | New sewer stub fee | Time and materials | |
(e) | Hazardous conditions | Additional time and materials | |
(f) | Road crossing | ||
(i) | County permit fee (if applicable) | Set by County | |
(ii) | Plus additional base fee | $1,500.00 | |
(iii) | Road crossing | Time and materials | |
(g) | Reconnection charge due to nonpayment or physical disconnect | ||
(i) | Water | $200.00 | |
(ii) | Sewer | $400.00 | |
(iii) | Off-hour reconnection charge (in addition to above) | $100.00 | |
(h) | Temporary shut-off and reconnection charge | $150.00 | |
(4)
Utility Main Charges. When connecting to all existing sewer or water mains additional charges may be added for costs associated with the original construction of the sewer or water main (see TTC § 13.35.030).
(6)
Miscellaneous Charges.
(a) | Customer assistance (after hours) | Time and materials |
$100.00 minimum | ||
(b) | Delinquent bill fee | $15.00 per month |
(c) | Equipment damage | Time and materials |
$100.00 minimum | ||
(d) | Meter testing | $20.00 if meter is not faulty |
(e) | Plan review (application filed) | Per lot: $50.00 |
(f) | Returned checks for insufficient funds | $40.00 |
(g) | Septic tank pump-outs | $400.00 for less than 1,000 gallons |
$500.00 for more than 1,000 gallons | ||
$700.00 if fills truck | ||
(h) | Temporary hydrant service | Time and materials (for hydrant and meter hook-up), plus water usage charge, plus $500.00 damage deposit |
(i) | Plan reviews: on-site inspection and testing | One-hour minimum = $300.00 |
(j) | Fire protection fee | $3.00 |
(Ord. 76 Appx. A, 12-6-2004 (Res. 2004-467); Res. 2016-164; Res. 2017-178; Res. 2019-233)