In any area where walks, curbs, or curbs and gutters do not exist, the engineering and inspection of driveways or approaches shall be the same as for a sidewalk, curb or gutter. In the event the driveway or driveway approach is being constructed in conjunction with sidewalk, curb or curb and gutter construction, the engineering and inspection shall be considered coincidental to the sidewalk, curb, or curb and gutter construction and no separate permit shall be required. In the event the driveway or approach is being added in an existing sidewalk, curb, or curb and gutter area, the person making the improvement, his contractor or his agent shall notify the DPW in writing at least 24 hours in advance of the time work will commence and also when paving and surfacing work is to commence. The DPW or his designated assistant shall check any forms as to line and grade and inspect the work until the same is completed.
(Ord. 649 Ch. IX § 6, 1967)